Štěchovice Reservoir
The construction started before World War II and because of the need for electricity resources were allocated for the project in spite of general shortage. The power station was put in action in 1943. The reservoir had flooded St John's Rapids (Svatojánské proudy).
The main role of the reservoir is to balance the water runoff from peak-load power station at Slapy Reservoir and to propel two Kaplan turbines with total installed power 2 x 11.25 MW (Štěchovice I). A lock (20.1 m difference between water levels, length 118 m) handles ships with displacement up to 1,000 tons.
The reservoir is also used by the pumped-storage hydroelectric plant Štěchovice II whose upper reservoir was created on the top of hill Homole. The plant was set in operation in 1947 and closed in 1991 due to obsolescence. From 1992 to 1996 a new hydroelectric plant using the reservoirs was built. This plant uses reverse Francis turbine with power 45 MW.
During 2002 floods the turbines of both power plants were severely damaged. After overhaul the plants were put back in production in 2004 and 2005 respectively.
Technical parameters of the reservoir
- height of the dam: 22.5 m
- length of the dam arch: 124 m
- held back water stretches 9.4 km
- reservoir area: 95.7 hectares
- water capacity: 11.2 million m³
- located on 84.4 km of the river
References
External links
- Overview on website of the operator, ČEZ (en, cz, de)
- Overview on website of Vltava River Authority (in Czech)
- Overview on website of Štěchovice village Archived 2007-03-22 at the Wayback Machine (in Czech)