Changjiang Nuclear Power Plant
History
Construction of the first phase of the plant which consists of two reactors was approved by the National Development and Reform Commission in July 2008. Site works began in December 2008 and the first concrete was poured at the first unit on 25 April 2010. The plant was built by China National Nuclear Corporation and China Huaneng Group. Unit 1 was connected to the electricity grid on 7 November 2015 and is commercially operating starting on 25 December 2015.
In July 2019 China National Nuclear Corporation announced it would start building a demonstration ACP100 small modular reactor on the north-west side of the site by the end of the year.
Technical features
The plant will be built in two phases, both consisting of two CNP-600 pressurized water reactors, with a capacity of 650 MW each. The first unit was connected to the grid November 7, 2015 and second unit June 20, 2016. More than 70% of the equipment was planned to be indigenously made.
Second phase
On September 2, 2020, Premier Li Keqiang of the State Council presided over an executive meeting of the State Council. The meeting approved the Hainan Changjiang Nuclear Power Phase II project. The total planned investment of the project is 39.45 billion yuan. Unit 3 is scheduled to pour the nuclear island's first concrete in August 2020 and will be completed in 2025; Unit 4 is scheduled to pour the nuclear island's first concrete in May 2021 and will be completed in 2026.
Reactor data
Unit | Type | Net power |
Gross power |
Thermal power |
Construction start |
First criticality |
Grid connection |
Operation start |
Notes |
---|---|---|---|---|---|---|---|---|---|
Phase I | |||||||||
Changjiang 1 | CNP-600 | 601 | 650 | 1930 | 2010-04-25 | 2015-10-12 | 2015-11-07 | 2015-12-25 | |
Changjiang 2 | CNP-600 | 601 | 650 | 1930 | 2010-11-21 | 2016-06-09 | 2016-06-20 | 2016-08-12 | |
Phase II | |||||||||
Changjiang 3 | Hualong One | 1000 | 1197 | 3190 | 2021-03-31 | 2026 | |||
Changjiang 4 | Hualong One | 1000 | 1197 | 3190 | 2021-12-28 | 2026 | |||
Changjiang 5 | Linglong One | 100 | 125 | 385 | 2021-07-13 | 2026 |
Pumped storage hydroelectricity
The 600 MW Hainan Qiongzhong pumped-storage hydroelectric plant helps to balance the nuclear plant by absorbing nighttime production and generating electricity during the day.
See also
- List of major power stations in Hainan province
- Nuclear power in China
- List of nuclear reactors#China
References
- ^ "Nuclear power plant in southern China begins construction". People's Daily. 2010-04-27. Retrieved 2010-05-01.
- ^ "Construction start at Hainan plant". World Nuclear News. 2010-04-26. Retrieved 2010-05-01.
- ^ Jim Bai; Tom Miles (2010-04-26). "CNNC says starts building Changjiang nuclear plant". Reuters. Archived from the original on March 3, 2016. Retrieved 2010-05-01.
- ^ "China's Changjiang 1 enters commercial operation". World Nuclear News. 30 December 2015. Retrieved 6 February 2016.
- ^ "CNNC launches demonstration SMR project". World Nuclear News. 22 July 2019. Retrieved 22 July 2019.
- ^ "Two nuclear power projects in China approved by the State Council". Seetao. 3 September 2020. Retrieved 13 January 2021.
- ^ "Changjiang 1". Power Reactor Information System. International Atomic Energy Agency. 2016-08-18. Retrieved 19 August 2016.
- ^ "Construction starts on second Hainan reactor". World Nuclear News. 2010-11-22. Retrieved 2010-11-22.
- ^ "Changjiang 2". PRIS. IAEA. 2016-08-18. Retrieved 19 August 2016.
- ^ "Nuclear Power in China". Information Papers. World Nuclear Association (WNA). September 2020. Retrieved 2020-09-07.
- ^ "Construction starts on second phase of Changjiang plant". World Nuclear News. 31 March 2021. Retrieved 2021-04-04.
- ^ "Changjiang 2". PRIS. IAEA. 2021-04-24. Retrieved 25 Apr 2021.
- ^ "Alstom to outfit China's 600-MW Hainan Qiongzhong pumped-storage plant" HydroWorld, 2014. Retrieved: 21 January 2015.