Chatfield Dam
Construction
In 1966, the U.S. Atomic Energy Commission projected a total federal cost of $74 million. Construction of the project was begun in 1967 and the dam was completed in 1975.
The massive breastworks of the dam measure approximately 13,136 feet (4,004 m) in length with a maximum height of the dam of 135 feet (41 m) above the streambed. The normal depth of the lake is 59 feet (18 m) at its deepest point. This means the dam towers 88 feet (27 m) above the mean surface of the reservoir.
The lake drains an area of more than 3,000 square miles (8,000 km). The 1,500 acre (6 km) lake has a conservation storage capacity of 27,000 acre⋅ft (0.033 km) with a flood-control pool of over 350,000 acre⋅ft (0.43 km).
The reservoir inundated the abandoned roadbed of the Colorado and Southern Railway, a historic narrow gauge line active between 1874 and 1942. Until 1899, it was part of the Denver, South Park and Pacific Railroad. The roadbed is still visible extending from the southern shore into the water just west of the inlet.
Chatfield Reservoir Reallocation Project
The Chatfield Reservoir Reallocation Project, a US$171 million construction project that took place between 2017 and 2020, created an additional 20,600 acre-feet (25,400,000 cubic meters) of water storage in the reservoir, raising its level by about 12 feet (3.7 meters). The project involved moving some of the surrounding park's facilities back from the new, higher lake levels.
Precautions were put into place during the Reallocation Project to adjust the timing and amount of water releases in a good faith manner in order to avoid impacting the walleye and smallmouth bass spawning during the spring. Best management practices were also used to minimize the spread of noxious and invasive weeds during water level fluctuations and soil disturbances due to the new construction.
On May 19, 2023, a new high water mark milestone was achieved as part of the Reallocation Project - reaching 5,444 feet above sea level. This increase in the water level has expanded the overall reservoir footprint resulting in some of the cottonwood trunks to now be below the water's surface and providing more locations for kayaking and paddle boarding.
Flood Risk Mitigation
During normal operations, the water released from Chatfield Reservoir to downstream users is less than 500 cubic feet of water (cfs) per second. During times of flood risk due to high snow runoff, the outlet structure can release up to 8,400 cfs. The structural design of the spillway was created to pass up to an additional 184,000 cfs in extreme flooding risk.
Chatfield State Park
The reservoir is surrounded by Chatfield State Park, a recreation area with boating, horseback riding, swimming, paddle boarding, fishing, biking, horseback riding, and camping. A secondary inflow from the south is Plum Creek. A tertiary inflow from the west is Deer Creek.
There are 212 bird species that are frequently found at Chatfield Reservoir. These birds either permanently live there or just go there to rest after long migrations. There is a Chatfield bird watch list that anyone can access. The bald eagle, white pelican and burrowing owl have been seen.
Environmental Issues
The Chatfield Reservoir is routinely monitored in three areas: the Reservoir Centroid, the South Platte Arm, and the Plum Creek Arm, which is overseen by the Colorado Department of Public Health and Environment. The water is tested for unhealthy levels of phosphorus, chlorophyll-a, nutrients, constituents of concern, total suspended solids, temperature, and specific conductance that could cause harm to the people and animals that use the body of water.
There have been several irregular test results for E. coli bacteria in recent years that ended up temporarily closing the swim beach at Chatfield State Park. Generally, closures are not a common occurrence, but can be caused by fecal waste from wildlife, run-off from urban areas, or excessive run-off from recent rainfall.
The Colorado Senate Bill SB23-267 was signed by Colorado Governor Jared Polis on June 6, 2023, creating the Chatfield State Park Water Quality Fee. The fee was created to help fund the Chatfield Watershed Plan which identifies opportunities to address chemical, physical and biological pollutants. Pollutants such as runoff from wildfire burn areas, phosphorus outbreaks from degraded upstream banks, and runoff from nearby agricultural land and septic systems.
See also
References
- ^ "Chatfield Project Statistics".
- ^ "CQ Alamanc 1966". cqpress.com. Congressional Quarterly. 1967. Retrieved 15 June 2016.
- ^ "State and Federal Partners Finalize Chatfield Reservoir Reallocation Project with Environmental, Agricultural, Recreational Benefits". Colorado Water Conservation Board. Colorado Department of Natural Resources. 2020-05-13. Retrieved 2021-08-05.
- ^ Rubino, Joe (2017-06-27). "Chatfield Reservoir expansion project will start this fall". The Denver Post. Retrieved 2017-07-19.
- ^ "Project Overview". Chatfield Storage Reallocation Project. Retrieved 2017-07-19.
- ^ https://chatfieldreallocation.org/wp-content/uploads/2017/04/fwrMitigationPlan.pdf
- ^ https://www.denverwater.org/tap/introducing-your-new-expanded-chatfield-reservoir?size=n_21_n
- ^ https://www.nwo.usace.army.mil/Missions/Dam-and-Lake-Projects/Tri-Lakes-Projects/Chatfield-Dam/#:~:text=Chatfield%20Dam%20and%20Lake%20was,inundated%20the%20region%20for%20centuries.
- ^ "Nature". Colorado Parks and Wildlife. Retrieved 2014-10-21.
- ^ "Monitoring".
- ^ "Cherry Creek State Park swim beach closed due to E. Coli as Chatfield reopens following one-day closure". 17 July 2019.
- ^ "Cherry Creek State Park swim beach closed due to E. Coli as Chatfield reopens following one-day closure". 7 July 2021.
- ^ https://leg.colorado.gov/sites/default/files/2023a_267_signed.pdf
External links
- Tri-Lakes Projects (Official site) - U.S. Army Corps of Engineers
- Chatfield Lake Area Map - Colorado Parks & Wildlife
- Chatfield conditions and fishing reports
- Chatfield Storage Reallocation Project website