Coventry Power Stations

The two Coventry power stations supplied electricity to the county borough of Coventry and the wider Warwickshire area from 1895 to 1976. They were owned and operated by Coventry Corporation until the nationalisation of the British electricity supply industry in 1948. The first power station was established in 1895 off Sandy Lane north of the city centre. A new larger power station was built at Longford / Hawksbury Junction in 1928 and was extended in 1938 and 1941. The Longford station was decommissioned in October 1976.

History

In 1891 Coventry Corporation applied for a provisional order under the Electric Lighting Acts to generate and supply electricity to the borough of Coventry. This was granted by the Board of Trade and was confirmed by Parliament through the Electric Lighting Orders Confirmation (No. 4) Act 1891 (54 & 55 Vict. c. lii). The power station was built in Sandy Lane adjacent to the Coventry Canal (52°25′04″N 1°30′43″W / 52.41778°N 1.51194°W / 52.41778; -1.51194), facilitating the supply of coal by barge. The generating station first supplied electricity in November 1895. The station was extended several times especially during the First World War to meet increased demand for electricity especially from munitions factories.

Further demand for electricity in the inter-war period led to a larger power station being built in 1926–28 in Aldermans Green Road, Longford (52°27′23″N 1°28′03″W / 52.45639°N 1.46750°W / 52.45639; -1.46750) five miles north-east of Coventry. This was also extended several times in 1938 and 1941.

Equipment specification

Coventry (Sandy Lane) power station

The original plant at Coventry (Sandy Lane) power station comprised horizontal engines coupled by ropes to Fowler dynamos. In 1898 the generating capacity was 350 kW and the maximum load was 126 kW.

First World War plant

During the First World War new plant was installed to meet growing demand for electricity. Coventry was a major armaments centre and there was a three-fold increase generating capability during the war. By 1923 the generating plant at Coventry comprised:

These machines gave a total generating capacity of 25,200 kW of alternating current.

A variety of electricity supplies were available to consumers:

  • 2-phase, 50 Hz AC at 6,600, 2,000 and 200 Volts.

Coventry (Longford) power station 1928

Longford Generating Station on a target dossier of the German Luftwaffe, 1939

A new power station at Longford / Hawkesbury Junction was sanctioned in August 1926 and was commissioned in October 1928.

The main contractors for the works were British Thomson-Houston Company of Rugby. Sub-contractors included Cleveland Bridge & Engineering Company, Wilson Lovatt, Stirling Boiler Company, and Pirelli-General Cable work.

The engine room and boiler house were constructed on mass concrete foundations. The buildings were steel framed with infill of brick and artificial stone. The coal handling equipment was capable of handling 50 tons an hour from the canal or from the railway sidings.

The station was officially opened on 31 October 1928.

The initial configuration of plant was:

  • Boilers:
    • 6 × Stirling tri-drum boilers with chain grate stokers, each producing 50,000 lb/h (6.3 kg/s) of steam, steam conditions were 325 psi and superheat to 700°F (22.4 bar, 371°C), steam was supplied to:
  • Turbo-alternators:
  • Cooling towers:
    • 4 × hyperbolic cooling towers each with a capacity of 600,000 gallons per hour (0.76 m/s), make up water was drawn from the adjacent Oxford Canal.

Coal was delivered by barge from the canal, and via a siding off the Coventry to Nuneaton railway line.

First and second extensions

These extensions to the power station comprised:

  • Boilers:
    • 4 × John Thompson tri-drum boilers with chain grate stokers, each producing 150,000 lb/h (18.9 kg/s) of steam, steam conditions were 325 psi and superheat to 720°F (22.4 bar, 382°C), steam was supplied to:
  • Turbo-alternators:
    • 2 × British Thomson-Houston 30.75 MW turbo-alternators, 3,000 rpm generating at 33 kV.
  • Cooling towers:
    • 2 × hyperbolic cooling towers each with a capacity of 1.5 million gallons per hour (1.89 m/s), arranged in a lozenge plan with the 1928 towers.

Third extension

This extension comprised:

  • Boilers:
    • 2 × John Thompson tri-drum boilers with chain grate stokers, each producing 150,000 lb/h (18.9 kg/s) of steam, steam conditions were 325 psi and superheat to 720°F (22.4 bar, 382°C), steam was supplied to:
  • Turbo-alternator:
    • 1 × British Thomson-Houston 30.75 MW turbo-alternator, 3,000 rpm generating at 33 kV
  • Cooling tower:
    • 1 × hyperbolic cooling tower with a capacity of 1.5 million gallons per hour (1.89 m/s).

Operations

In 1898 the maximum electricity demand on the Sandy Lane station was 126 kW. 79.583 MWh of electricity was sold to 100 customers and there were 8,149 lamps on the circuits. The revenue in 1898 was £5,018 and the operating expenditure was £1,166.

Operating data 1921–23

The operating data for the period 1921–23 is summarised in the table:

Coventry power station operating data 1921–23
Electricity Use Units Year
1921 1922 1923
Lighting and domestic use MWh 2,873 2,709 3,195
Public lighting use MWh 46 72 99
Traction MWh 502 403 579
Power use MWh 28,003 22,950 30,952
Total use MWh 31,425 26,135 34,826
Load and connected load
Maximum load kW 17,815 16,250 18,800
Total connections kW 41,806 42,706 44,043
Load factor Per cent 23.6 21.7 23.9
Financial
Revenue from sales of current £ 234,778 201,124
Surplus of revenue over expenses £ 62,220 99,930

The data shows the general growth of demand and use of electricity.

Under the terms of the Electricity (Supply) Act 1926 the Central Electricity Board (CEB) was established in 1926. The CEB identified high efficiency ‘selected’ power stations that would supply electricity most effectively; Coventry was designated a selected station. The CEB also constructed the National Grid (1927–33) to connect power stations within a region.

Operating data 1946

Coventry (Longford) power station operating data in 1946, just prior to nationalisation, was as follows:

Coventry power station operating data, 1954–72
Year Load factor per cent Max output load MW Electricity supplied GWh Thermal efficiency per cent
1946 34.9 91,060 278.69 16.55

The British electricity supply industry was nationalised in 1948 under the provisions of the Electricity Act 1947. The Coventry electricity undertaking was abolished, ownership of Coventry power station was vested in the British Electricity Authority, and subsequently the Central Electricity Authority and the Central Electricity Generating Board (CEGB).

At the same time the electricity distribution and sales responsibilities of the Coventry electricity undertaking were transferred to the East Midlands Electricity Board (EMEB).

Operating data 1954–72

Operating data for the period 1954–72 is shown in the table:

Coventry power station operating data, 1954–72
Year Running hours or load factor (per cent) Max output capacity MW Electricity supplied GWh Thermal efficiency per cent
1954 3687 120 157.219 16.98
1955 4237 120 199.893 17.40
1956 4269 120 199.074 17.32
1957 4153 111 184.495 17.60
1958 3940 111 179.904 18.01
1961 (12.6 %) 117 129.267 17.97
1962 (13.9 %) 117 142.590 17.45
1963 (17.87 %) 117 183.105 17.60
1967 (13.1 %) 117 134.059 16.05
1972 (11.3 %) 84 83.81 16.33

The data demonstrates the declining usage, capacity and supply over the period 1954–72.

Closure and redevelopment

The Sandy Lane power station buildings, renamed Electric Wharf, have been redeveloped as residential and commercial use.

Coventry (Longford) power station was decommissioned on 25 October 1976. The buildings and structures were subsequently demolished and as of 2020 the area is unused. However, the location's association with electricity continues. East of the Oxford Canal is the 275 kV Coventry substation that feeds the 132 kV Coventry North substation south of the former power station site.

See also

References

  1. ^ "Local Acts of Parliament 1891". legislation.gov.uk. Retrieved 10 October 2020.
  2. ^ Hannah, Leslie (1979). Electricity before Nationalisation. London: Macmillan. p. 59. ISBN 0333220862.
  3. ^ Garrett, Frederick (1959). Garcke's Manual of Electricity Supply. Vol. 56. London: Electrical Press. pp. A-47, A-118.
  4. ^ Garcke, Emile (1898). Manual of Electrical Undertakings 1898-99 vol. 3. London: P. S. King and Son. pp. 160–162.
  5. ^ Electricity Commissioners (1925). Electricity Commissioners, Electricity Supply – 1920–23. London: HMSO. pp. 26–9, 366–71.
  6. ^ "Coventry power station opened". The Times. 1 November 1928. p. 11.
  7. ^ "Coventry (Longford) power station". warwickshirerailways.com. Retrieved 10 October 2020.
  8. ^ Ordnance Survey 25 inch map Warwickshire XVII.13 (Bedworth; Coventry; Shilton) revised 1938, published 1947
  9. ^ "Electricity (Supply) Act 1926". legislation.gov.uk. 1926. Retrieved 10 October 2020.
  10. ^ Electricity Council (1987). Electricity supply in the United Kingdom: a Chronology. London: Electricity Council. pp. 45, 60, 69, 73. ISBN 085188105X.
  11. ^ Electricity Commissioners (1947). Generation of Electricity in Great Britain Year Ended 31 December 1946. London: HMSO. p. 7.
  12. ^ "Electricity Act 1947". legislation.gov.uk. Retrieved 10 October 2020.
  13. ^ CEGB Annual report and Accounts, 1961, 1962 & 1963
  14. ^ CEGB (1972). CEGB Statistical Yearbook 1972. London: CEGB. p. 13.
  15. ^ "Electric Wharf history". Retrieved 10 October 2020.
  16. ^ UK Parliament written answers Coal-fired power stations 16 January 1984
  17. ^ "Open infrastructure map". Open infrastructure map. Retrieved 10 October 2020.