Dharasu Power Station
Background
The power station is stage two of the Maneri Bhali Hydroelectric Project which was planned in the 1960s. In 1979, construction on stage two began. In 1984, the first stage, the 90 MW Tiloth Power Plant located upstream at Uttarkashi at 30°43′36″N 78°26′44″E / 30.72667°N 78.44556°E was completed. Dharasu, the second stage was halted in 1990 due to funding issues and was not restarted until 2002. The power station was eventually completed and commissioned by 2008.
Design
Water supplied to the power station is first diverted from the Bhagirathi River into a 16 km (10 mi) long tunnel by the 81 m (266 ft) long Bhali (Joshiyara) Dam located upstream near Bhali at 30°43′46″N 78°25′25″E / 30.72944°N 78.42361°E. The difference in elevation between the barrage and the power station affords a design hydraulic head of 247.6 m (812 ft) and gross head of 285 m (935 ft). The water powers four 76 MW Francis turbine-generators before being discharged back into the river. The design discharge of the power station is 142 m/s (5,015 cu ft/s).
See also
References
- ^ "Power from Maneri Bhali by year-end". Outlook India. 12 March 2006. Retrieved 11 July 2011.
- ^ "Dharasu HEP (4x76=304 MW)". Uttaranchal Jal Vidyut Nigam Limited. Archived from the original on 27 December 2009. Retrieved 11 July 2011.
- ^ "The Challenge and Status of The Maneri Bhali Stage-II Hydroelectric Project". Uttaranchal Jal Vidyut Nigam Limited. Archived from the original on 11 September 2011. Retrieved 12 July 2011.