Gateway Station (Charlotte)
History
In 1991, the City of Charlotte and the North Carolina Department of Transportation (NCDOT) completed a preliminary feasibility study for a new Uptown rail station to replace the existing Amtrak station, built in 1962 by the Southern Railway and located on North Tryon Street near the rail yard for SOU's successor, Norfolk Southern. The site chosen along West Trade Street, currently a Greyhound station since 1973, was once the location of three previous stations: the Atlanta & Charlotte Depot (prior to 1886), the Richmond and Danville Depot (1886-1905) and the Southern Depot (1905-1962).
In 1998, NCDOT began the acquisition of property for the station and supportive land uses (i.e. retail and offices). In 2002, NCDOT completed its feasibility study for the Charlotte Multi-Modal Station and Area Track Improvements. The study identified two possible options: The Preferred Alternative, which included the station, various track work and a greenway at $206.8 million (2002 dollars), and the Station Build Only Alternative at $109.6 million (2002 dollars). By 2004, NCDOT had completed property acquisition of 27-acre (110,000 m).
Announced publicly in August 2005, the proposed Gateway Station is envisioned to serve as both a multimodal transit center in addition to both office and retail space. As originally presented, the station would feature an underground station for CATS buses, a 100,000-square-foot (9,300 m) office building, and soaring lobby for other rail and bus services in the building's atrium.
In 2009, the American Recovery and Reinvestment Act of 2009 awarded $520 million grant for the Piedmont Improvement Project in North Carolina; which was used to make rail improvements identified in the 2002 feasibility study. In that same year, an Environmental impact assessment was completed that resulted in a Finding of No Significant Impact (FONSI) and the City of Charlotte and NCDOT signed a municipal agreement.
In 2012, NCDOT completed property acquisition again of approximately 18-acre (73,000 m) for the Charlotte Gateway Station project. On November 1, 2012, NCDOT selected Houston-based developer, the Hines Group, for the project. In 2015, NCDOT won a $25 Million TIGER Grant, to help start construction of Gateway Station.
On August 30, 2021, the streetcar station was opened as part of the second phase of the CityLynx Gold Line.
The station's inter-city tracks and platform were completed in November 2022. The first test run of a Piedmont train using the station occurred on November 29, 2022.
Station plans
The station was built with a streetcar platform, which provides connection to the CityLynx Gold Line, and a 1,100 ft (340 m) long, fully ADA compliant high-level platform, the second in the state behind Raleigh Union Station, for Amtrak service. It will be the southern terminus of Amtrak's Carolinian and Piedmont lines, as well as a service stop on Amtrak's Crescent and a major stop on the planned Southeast High Speed Rail Corridor. It will significantly improve connections between Amtrak and local transit. CATS plans for the station to be a stop on the Lynx Silver Line. An adjacent, interim bus station was built for Greyhound, which provides connections to routes running to Atlanta, Detroit, Jacksonville, New York City and Philadelphia.
Construction
Both the Charlotte Area Transit System (CATS) and NCDOT have started/completed various projects that impact the future station, including the CityLynx Gold Line and a new Locomotive and Railcar Maintenance Facility located on West Summit Avenue. However, groundbreaking for the Charlotte Gateway Station did not begin until July 2018. The project is using a phased implementation approach to facilitate the near-term development of the rail station while also setting the stage for private development to occur. There are three general phases with additional sub-phases.
Phase 1
At an estimate cost of $91.3 million (2017 dollars), the first phase has two parts:
- 1A) Construct 2,000 feet (610 m) of track, structures, and signals to support two new station tracks; construct retaining wall/earthwork; construct temporary intercity bus facility (completed August, 2019).
- 1B) Construct rail platform and canopy for passenger loading/unloading.
Construction of Phase 1 was completed in November 2022.
Phase 2
At an estimate cost of $49.9 million (2017 dollars), the second phase has two parts:
- 2A) Construct platform canopy; construct station building (interim condition) with full construction of concourse level and core and shell only for plaza and mezzanine levels; construct temporary surface parking and passenger drop-off area.
- 2B) Decommission existing Amtrak station on North Tryon Street.
This phase is partially funded with capital carryover from phase 1.
Phase 3
At an estimate cost of $658.9 million (2017 dollars), the third phase has three parts:
- 3A) Construct greenway connection with bridge over Fourth Street, vertical circulation and retaining walls; construct bus facility, which includes structured parking and residential over retail wrapping garage (facility will serve as temporary parking for rail passengers till phase 3B is completed).
- 3B) Complete upper section of station building; extend greenway with bridge over Trade Street, vertical circulation and retaining walls; extend greenway to Bank of America Stadium; construct private development around station.
- 3C) Construct remote properties between Fifth and Seventh Streets; extend greenway to Ninth Street.
This phase is currently not funded, but is expected to be developed mostly by private developers.
Station layout
As of December 2, 2022, the station consists of one island platform in the center of Trade Street, for Gold Line service, and it is located on what will become the front entrance of the intermodal station. A second, high-level island platform is located alongside Norfolk Southern's tracks for Amtrak service, which will not be publicly accessible until 2025-27.
References
- ^
"Charlotte Bus Station". Greyhound Lines. Retrieved August 12, 2023.
518 West 4th Street. Charlotte, NC 28202
- ^ "CityLYNX Gold Line". Charlotte Area Transit System (CATS). Retrieved August 30, 2021.
- ^ Passenger Rail Developments in North Carolina. High Speed Rail Alliance. July 28, 2023. Retrieved August 8, 2023 – via YouTube.
- ^ "Charlotte Gateway Station - Multimodal Station Area Plan - Final Report" (PDF). Charlotte Area Transit System. July 2017. Retrieved May 8, 2018.
- ^ "Charlotte Multi Modal Station Project Timeline". NCDOT Rail Division. Archived from the original on June 18, 2008. Retrieved June 17, 2008.
- ^ "Gateway Station / CGS Project Background". Charlotte Area Transit System (Press release). Archived from the original on August 30, 2008. Retrieved June 17, 2008.
- ^ "Feasibility Study for the Charlotte Multi-Modal Station and Area Track Improvements" (PDF). Charlotte Area Transit System. July 2002. Archived from the original (PDF) on August 15, 2008. Retrieved May 8, 2018.
- ^ Whitacre, Dianne (August 24, 2005). "CATS plans $100 million transit hub". The Charlotte Observer. p. 1A.
- ^ Rainey, Amy (January 16, 2008). "The Ever-Changing Face of the Queen City - Here's the Scoop on Some Projects Going Up, in and Around Your Neighborhood". The Charlotte Observer. p. 10Z.
- ^ "Plan for new Greyhound bus station moving along". Charlotte, NC: WCNC-TV. Archived from the original on 2013-02-09.
- ^ "Charlotte to move Amtrak station uptown with federal grant". The Charlotte Observer. October 29, 2015. Retrieved October 30, 2015.
- ^ WBTV Web Staff (August 30, 2021). "CityLYNX Gold Line streetcar officially up and running". WBTV. Retrieved August 30, 2021.
- ^ "Charlotte Gateway Station: Phase 1". Raleigh, NC: NCDOT. November 2, 2022. Archived from the original on December 2, 2022. Retrieved December 2, 2022.
- ^ Brierton, James (December 1, 2022). "First test train arrives at Charlotte's Gateway Station". Charlotte, NC: WCNC. Archived from the original on December 2, 2022. Retrieved December 2, 2022.
- ^ "Gateway Station Phase 1". Retrieved November 23, 2019.
- ^ Portillo, Ely (17 July 2018). "Charlotte's breaking ground on a new uptown train station this week". The Charlotte Observer. Retrieved 17 July 2018.
- ^ Fahey, Ashley (19 February 2017). "Infrastructure phase of Gateway Station is 60% complete; master design plan to be presented this summer". Charlotte Business Journal. Retrieved 25 May 2021.
- ^ Harrison, Steve (January 9, 2018). "After two decades, an uptown transit hub is moving forward. Here's the vision". The Charlotte Observer. Retrieved May 9, 2018.
- ^ "Work continues on Charlotte's new Gateway Station". Spectrum News 1 North Carolina. 2021-04-30. Retrieved 2021-06-29.
External links
- Media related to Gateway Station (Charlotte) at Wikimedia Commons
- Gateway Station Home