Granville Harbour Wind Farm
Granville Harbour Wind Farm is a wind farm operated by Palisade Investment Partners, on the west coast of Tasmania, Australia.
The facility first generated to the grid on 27 February 2020 with the completion of its first turbine, with the site being fully commissioned and operational in December 2020. The wind farm has 31 wind turbines and have a maximum capacity of 112 MW.
It is located on a site 35 kilometres (22 mi) northwest of Zeehan, Tasmania.
Operations
The generation table uses eljmkt nemlog to obtain generation values for each month. Grid connection started in January 2020, and was fully commissioned in December 2020.
Year | Total | Jan | Feb | Mar | Apr | May | Jun | Jul | Aug | Sep | Oct | Nov | Dec |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|
2020 | 216,847 | 0* | 704* | 5,265* | 11,461* | 22,341* | 29,220* | 23,440* | 78* | 35,447* | 22,415* | 30,988* | 35,488* |
2021 | 408,465 | 29,023 | 24,288 | 28,624 | 33,850 | 41,981 | 31,432 | 41,395 | 47,711 | 39,424 | 38,754 | 24,846 | 27,137 |
Note: Asterisk indicates power output was limited during the month.
See also
References
- ^ "Newest Tasmanian wind farm fully operational". 18 December 2020. Archived from the original on 12 January 2021. Retrieved 10 January 2021.
- ^ "Granville Harbour Wind Farm". 2018. Archived from the original on 25 February 2020. Retrieved 27 February 2020.
- ^ "Construction underway at Tasmania's Granville Harbour wind farm". RenewEconomy. 8 April 2019. Archived from the original on 28 May 2019. Retrieved 28 May 2019.