Construction on the dam began in May 2003 and the river was diverted in October 2004. Reservoir filling began in 2007 and by 2008, the dam and power plant were complete. On June 28, 2010, a landslide in the area of the dam that killed 99 locals was believed to be caused by seismic effects from the reservoir.
Specifications
The dam is 200.5 metres (658 ft) tall and 410 metres (1,345 ft) wide and composed of roller-compacted concrete. It also contains three spillway chutes on its surface. Each spillway is controlled by a 16 metres (52 ft) wide and 20 metres (66 ft) tall floodgate and they have a combined maximum discharge of 9,857 cubic metres per second (348,097 cu ft/s). The dam also contains a bottom outlet works for draining the reservoir which a maximum discharge capacity of 799 cubic metres per second (28,216 cu ft/s).
See also
References
- ^ "Guangzhao Hydropower Project" (PDF). Chinese National Committee on Large Dams. Retrieved 8 January 2011.
- ^ Xiao, Fan (July 15, 2010). "Chinese dam played role in deadly landslide". International Probe. Archived from the original on 13 July 2010. Retrieved 8 January 2011.