Highbank Power Station
On 16 June 1945Minister of Works, Bob Semple, opened the power station, and "set the 36,000bhp in motion".
theConstruction
The Highbank Power Station was constructed as part of the Rangitata Diversion Race (RDR) irrigation scheme by the Public Works Department.
The primary purpose of the RDR scheme was for the irrigation of farmland, not the generation of Electricity. This irrigation diversion race is the source of the water for the Highbank Power Station. When agricultural demand for water is low the water is used by the station to generate electricity, this is typically during the winter months.
Work began in the early 1940s, starting with the construction of an access road.
World War II
The outbreak of World War II saw the project delayed due to manufacturing, material, and manpower shortages. The projects completion in June 1945 had followed the completion of the RDR in September 1944.
An unfortunate event was the sinking by enemy action of the ship which was carrying to New Zealand the stator for the generator at Highbank. This necessitated the manufacture of a new stator in England.
1945 floods
There was considerable damage by flooding in the area of the Highbank irrigation and power scheme due to floods in February 1945, this necessitated the village of Highbank being relocated 390 m (0.24 mi) upstream of the powerhouse and a new approach road made.
Power House
Construction began in 1939 with the power house structure finished in 1942, The Modern Reinforced concrete structure is some 37 m (120 ft) long and 16 m (52 ft) wide. The height of approximately 16 m (52 ft) allowed for the installation of both the 90 Ton crane, and 10 Ton aux hoist.
Electrical Systems
Generator and Turbine
Both the Generator and Turbine were manufactured by English Electric co and installed from 1942 till the commissioning in 1945. The Generator installed was the largest in New Zealand at the time of its installation.
The single large vertical shaft generator is driven by a 36,000 bhp (27 MW) francis turbine at 300 rpm. The English Electric Generator is rated for 26.5MW of output with a synchronous speed of 300rpm, making it a 20 pole unit so as to match the 50hz of the National Grid
Transmission
The Highbank Power Station is connected to EA Networks 66kV network. The 66kV line is a spur line beyond Methven, connecting back to the Methven Substation "Methven66" (MTV). The power is generated at 11kV and stepped up to 66kV for transmission on site.
Upgrades
Early Years
In the 1970s the station generation capacity had reduced to approximately 65% of the original rated capacity due to sediment build-up and wear on mechanical components. This led to the turbine runner being replaced along with improvements in sediment control at the canal intake and ongoing removal of sediments to reinstate the original performance
BCI Pumps
TrustPower (now Manawa Energy) installed and operates river intake, fish screening, and pumping facilities to deliver the water from the Rakaia River to the RDR using some of the existing Highbank Power Station facilities. The Highbank Power Station has been equipped with an array of six 1.5 MW pumps that allow it to take water from the Rakaia River and pump it up the power station penstock 104 m (342 ft) into the RDR. The water is then available for irrigators to use.
TrustPower(now Manawa Energy) generation manager Mike Kedian believed pumping water back through the penstock was a New Zealand first.
Pumping water up hill is not without its challenges, and one of these is the volume and pressure of the water contained in the pipeline when being pumped. In order to protect the penstock from pressure fluctuations an air-chamber has been installed adjacent to the pump station to maintain pipeline pressure within acceptable bounds.
Generator and Turbine Replacement 2025
Manawa Energy plans to Replace the existing assets with 1 new 29MW turbine and a new generator. Replacement of both generator and turbine provide for a more efficient generation of electricity using the available water. (+8GWh pa). The project is estimated by Manawa Energy to take 18 months and cost NZ$30.5m, Replacement commenced October 2024. The nearly 80 year old equipment had reached end of life, along with the generator and turbine other mechanical and electrical equipment on the site will be replaced.
Synchrophasors
The Highbank generator being synchronized before being reconnected to the rest of the network is vital, The generator can suffer irreparable damage if it is not in sync. Manawa Energy shuts down the Highbank generator to guard against out of synchronism events before reconnecting, this protects the generator, but leads to inefficiencies and delays in bringing its capacity back online.
This project has been postponed until 2025.
See also
- National Grid (New Zealand)
- Hydroelectric_power_in_New_Zealand
- List of power stations in New Zealand
- Electricity sector in New Zealand
- New Zealand electricity market
References
- ^ Highbank Power Station. Wellington, N.Z. : Govt Print., 1958. 1958. Retrieved 2 January 2025.
- ^ "Rating Information Details". ADC. Ashburton District Council. Retrieved 2 January 2025.
- ^ "CRC011249 Consent for water discharge". ECAN. Environment Canterbury. Retrieved 2 January 2025.
- ^ "Highbank Power Scheme". Manawa Energy. Retrieved 2 January 2025.
- ^ New Zealand National Film Unit (19 September 2012). "Weekly Review No. 202 (1945)" (Video). Archives New Zealand. Retrieved 2 January 2025.
- ^ "EA NETWORKS ASSET MANAGEMENT PLAN 2023-33" (PDF). EA Network. EA Networks. Retrieved 2 January 2025.
- ^ "The Hydro Station.", The Ashburton Guardian, p. 4, 17 January 1940, retrieved 12 January 2025
- ^ "Floods during construction". New Zealand Historic Weather Events Catalogue. National Institute of Water and Atmospheric Research. Retrieved 3 January 2025.
- ^ "Power company invests in irrigation scheme" (PDF). worldpumps.com. Retrieved 3 January 2025.
- ^ "FY25 Interim Results Presentation" (PDF). Manawa Energy.
- ^ "Annual Shareholder Meeting 2023" (PDF). Manawa Energy. Retrieved 3 January 2025.