Kettle Generating Station
Construction on the station began in the spring of 1966 and it was carried out in several phases. First, the power house was constructed after a circular coffer dam was set on the right side of the river. Second, the spillway was built adjacent and to the left of the power house while the river flowed through the power house in the meantime. Once the spillway was complete the entire the river was diverted through it. At this point, the turbines and generators were loaded into the power house and the earth-fill section on the dam's left bank was completed. The first generator was commissioned in December 1970 and seven generators were operational in June 1973 when the station was officially opened. The last generator was commissioned in November 1974.
Of the river's 885 m (2,904 ft) width, the power house covers 380 m (1,247 ft) or 43 percent. The spillway covers 22 percent in the center of the dam and the earth-fill dam completes the remaining 35 percent in length. The dam's spillway is controlled by eight floodgates and can discharge up to 8,349 m/s (294,842 cu ft/s) of water. The power house contains twelve 102 MW propeller-type turbine-generators for an installed capacity of 1,220 MW. Each turbine can discharge up to 270 m/s (9,535 cu ft/s) and are afforded 30 m (98 ft) of hydraulic head.
See also
- List of largest power stations in Canada
- Long Spruce Generating Station – second dam downstream, completed in 1979
- Limestone Generating Station – third dam downstream, completed in 1990
References
- ^ "Kettle Generating Station". Manitoba Government. Archived from the original on 11 March 2012. Retrieved 4 March 2012.
- ^ "Kettle Generating Station". Manitoba Hydro. Retrieved 4 March 2012.
- ^ "Kettle Generating Station" (PDF). Manitoba Hydro. Retrieved 4 March 2012.
- ^ "Hydroelectric Plants in Manitoba". IndustCards. Retrieved 4 March 2012.