Kudgi Super Thermal Power Project
The coal for the plant will be derived from NTPC's Pakhri Barwadih coal block in Jharkhand.
The Construction Power required for stage-1 erection was drawn from M/s Hescom (Hubli Electricity Supply Company) through 2 no. of dedicated 33kV OH lines from Basavana Bagewadi and Mattihal substations of Hescom.
The water source is from reservoir of Almatti Dam which is constructed on Krishna River.
Capacity
Kudgi Super Thermal Power Project will have an installed capacity of 4000 MW (3x800 MW in first stage and 2x800 MW in second stage). Doosan Power systems India Pvt Ltd will supply Steam Generator for the plant & Toshiba JSW Power Systems Pvt Ltd will supply super-critical steam turbine and generator and L&T Howden will supply Axial fans to NTPC for the plant.
Stage | Unit Number | power (MW) | Date of Commissioning | Status |
---|---|---|---|---|
1st | 1 | 800 | 2016 Dec | Commissioned |
2 | 800 | 2017 March | Commissioned | |
3 | 800 | 2018 March | Commissioned. | |
2nd | 4 | 800 | Yet to be approved | |
5 | 800 | Yet to be approved |
References
- ^ "National Thermal Power Corporation Limited | Hydroelectricity Power Distribution Company". NTPC.co.in. 23 March 2015. Archived from the original on 7 January 2015. Retrieved 28 March 2015.
- ^ "Toshiba JSW to supply steam turbine for NTPC's Kudgi power project | Business Standard News". Business-standard.com. 21 February 2012. Retrieved 28 March 2015.
- ^ Market, Capital (26 December 2016). "NTPC commissions Unit- I of 800 MW of Kudgi STTP" – via Business Standard.
- ^ Market, Capital (23 March 2017). "NTPC commissions 2nd unit of 800 MW of Kudgi Super Thermal Power Station" – via Business Standard.
- ^ "2nd unit of NTPC project at Kudgi begins commercial operation". The Economic Times. 5 January 2018.