La Grande-1 Generating Station
The La Grande-1 (LG-1) is a hydroelectric power station on the La Grande River that is part of Hydro-Québec's James Bay Project. The station can generate 1,436 MW and was commissioned in 1994–1995. A run of the river generating station, it is one of only two generating stations of the James Bay Project that use a reservoir without any major water-level fluctuations (the Laforge-2 generating station is the other). Thus, the amount of electricity generated by the station depends almost entirely on the water-flow of the river, which is largely controlled by upstream reservoirs and generating stations.
See also
- List of largest power stations in Canada
- List of electrical generating stations in Quebec
- Reservoirs and dams in Canada
- Hydro-Québec
- James Bay Project
- Chisasibi, Quebec