MetroLink (St Louis)
MetroLink shares some characteristics of a light metro, rapid transit or semi-metro service, including a largely independent right-of-way, a higher top speed, and level boarding at all platforms.
In 2023, the system had an annual ridership of 6,717,900, or about 21,800 per weekday.
History
Construction on the initial 17-mile (27 km) MetroLink line from St. Louis Lambert International Airport to the 5th & Missouri station in East St. Louis began in 1990. The first 13.9-mile (22.4 km) segment opened on July 31, 1993, with 16 stations between North Hanley and 5th & Missouri. The extension to Lambert Airport Main opened on June 25, 1994. Three infill stations have since been added to this alignment: East Riverfront in 1994, Lambert Airport East in 1998, and Cortex in 2018.
About 14 miles (22.5 km) of the original 17-mile (27 km) alignment reused existing railroad right-of-way including historic downtown tunnels. The capital cost to build the initial phase of MetroLink was $465 million, including $348 million from the Federal Transit Administration (FTA).
Construction on the St. Clair County MetroLink extension from the 5th & Missouri station to the College station in Belleville began in 1998 and opened in May 2001. The extension added eight stations and seven park-ride lots. The total project cost was $339.2 million with $243.9 million paid by the FTA and $95.2 million paid by the St. Clair County Transit District (via a 1/2 cent sales tax passed in November 1993).
In May 2003, a 3.5-mile (5.6 km) extension from the College station to the Shiloh-Scott station opened. This $75 million project was funded by a $60 million grant from the Illinois FIRST (Fund for Infrastructure, Roads, Schools, and Transit) Program and $15 million from the St. Clair County Transit District.
The 8-mile (12.9 km) Cross County Extension opened on August 26, 2006 and added nine stations from Forest Park-DeBaliviere to Shrewsbury, Missouri. Intermediate stops include service to Washington University, Clayton, the Saint Louis Galleria and Maplewood. The entire project was funded by a $430 million Metro bond issue. Citing repeated delays and cost overruns, Metro fired and then sued its general contractor, Cross County Collaborative, in the summer of 2004. Metro sought $81 million in damages for fraud and mismanagement while the Collaborative counter-sued for $17 million for work that Metro hadn't paid for. On December 1, 2007, a jury awarded the Collaborative $2.56 million.
On October 27, 2008, Metro renamed the Lambert Airport branch the Red Line and the Shrewsbury branch the Blue Line. Blue Line service was also extended from its former terminus at Emerson Park to Fairview Heights. All trains have signs on the front and side that identify the train as a Red or Blue line train, and operators make live announcements identifying lines and stations.
On September 9, 2014, the United States Department of Transportation announced $10.3 million in funding for a new Metrolink station between the Central West End and Grand stations in the Cortex Innovation Community. An additional $5 million in funding was provided by a public-private partnership including Washington University, BJC HealthCare, Great Rivers Greenway and Cortex. The new Cortex station, located just east of Boyle Avenue, opened to the public on July 31, 2018.
On June 15, 2019, MetroLink set its single day ridership record when over 100,000 people used the service to attend the parade after the St. Louis Blues won the 2019 Stanley Cup playoffs.
On July 26, 2022, a flash flood shut down MetroLink for nearly 72 hours and caused roughly $40 million in damage. The flood damaged nearly 5 miles (8.0 km) of track bed, two elevators, two communications rooms, three signal houses and destroyed two MetroLink vehicles. By that September, normal Red Line service had resumed while restricted service continued on the Blue Line. On July 31, 2023, Metro received $27.7 million in federal emergency disaster relief funding to help cover the cost of restoration. In March 2024, Blue Line platform and speed restrictions were lifted after repairs on the last signal house were completed.
In 2023, Bi-State's board approved a memorandum of understanding authorizing the Metro team to plan and develop the Green Line expansion with the City of St. Louis. In May, Metro received a $196.2 million federal grant to purchase new light rail vehicles to replace the remaining SD-400 cars. Six months later, Bi-State's board approved a contract with Siemens Mobility worth up to $390.4 million for as many as 55 new S200 light rail vehicles with delivery expected to begin in 2027.
Chronology
Below is a list of dates on which segments of the MetroLink system opened for service.
Date | Event | Stations | Length |
---|---|---|---|
July 31, 1993 | Line opens between North Hanley and 5th & Missouri | 16 | 13.9 mi (22.4 km) |
May 14, 1994 | East Riverfront opens between existing stations | 1 | — |
June 25, 1994 | Extension to Lambert Airport Main opens | 1 | 3.15 mi (5.1 km) |
December 23, 1998 | Lambert Airport East opens between existing stations | 1 | — |
May 5, 2001 | Extension to College opens | 8 | 17.4 mi (28 km) |
June 23, 2003 | Extension to Shiloh-Scott opens | 1 | 3.5 mi (5.6 km) |
August 26, 2006 | Extension to Shrewsbury-Lansdowne I-44 opens | 9 | 8 mi (13 km) |
July 31, 2018 | Cortex opens between existing stations | 1 | — |
Total | 38 | 46 mi (74 km) |
Current rail lines
Red Line
The 38-mile (61 km) Red Line begins at St. Louis Lambert International Airport, making stops at the Terminal 1 and Terminal 2 stations. It proceeds through Kinloch, then stops at the North Hanley station near Bel-Ridge. It makes two stops (UMSL North & UMSL South) at the University of Missouri St. Louis in Normandy. After UMSL, trains run on the old Wabash/Norfolk & Western Railroad's Union Depot line that once brought passenger trains from Ferguson to Union Station. Traveling into Pagedale, it stops at the Rock Road station and then at Wellston's namesake station on Plymouth Street. Entering St. Louis City at Skinker Boulevard, the line stops at the Delmar Loop station and its namesake entertainment district. At the following station, Forest Park-DeBaliviere, the Red Line meets the Blue Line; the lines then share tracks until the Blue Line terminates at the Fairview Heights station in Illinois.
Blue Line
The 24-mile (38.6 km) Blue Line alignment starts at the Shrewsbury-Lansdowne I-44 station in Shrewsbury, just west of the River des Peres. It crosses over Interstate 44 and continues north to two stations in Maplewood, Missouri (Sunnen and Maplewood/Manchester). The line continues north to the Brentwood I-64 station in Brentwood, Missouri, just south of Interstate 64. It then proceeds in a tunnel underneath Interstate 64, continuing to the Richmond Heights station, which serves the Saint Louis Galleria shopping mall. The line then proceeds through a sharp turn east to the Clayton station in the median of Forest Park Parkway in Clayton, Missouri, where it serves the Central Business District of St. Louis County. It heads east to the Forsyth station where it enters a tunnel to the University City-Big Bend subway station. After crossing the St. Louis City/County boundary, the Blue Line stops at the Skinker subway station, the last stop serving nearby Washington University. At the following station, Forest Park-DeBaliviere, the Blue Line meets the Red Line. From this station, the two services share track until the Blue Line terminates at the Fairview Heights station in Illinois.
Shared alignment
In all, the Red and Blue lines share tracks for 16 stations. From west to east: the Central West End and Cortex stations that serve the Central West End neighborhood, Washington University Medical Center, and Cortex Innovation Community. The Grand station transfers with the busy #70 MetroBus line and serves Saint Louis University and its hospital. Next, the Union Station, Civic Center, Stadium, 8th & Pine, Convention Center, and Laclede's Landing stations serve downtown St. Louis and its many destinations. Crossing the historic Eads Bridge into Illinois, the line serves the East Riverfront, 5th & Missouri, Emerson Park, Jackie Joyner-Kersee Center, and Washington Park stations in East St. Louis, Illinois. At the next station, Fairview Heights, the Blue Line ends. The Red Line continues south through Belleville, Illinois, to its terminus at the Shiloh–Scott station near Scott Air Force Base.
Rolling stock
MetroLink operates 87 Siemens SD-400 and SD-460 light rail vehicles. Each 90-foot-long (27 m), single articulated vehicle has four high platform doors per side and can hold 72 seated and 106 standing passengers. The cars are powered by an electric motor which gets its electricity from an overhead line with a 750 V DC supply.
Each car has an enclosed operator cab at each end. This configuration is the most flexible for operations but prevents travel between cars. Each car has separate doors for boarding at station level and track level; in normal operations, the track-level doors (equipped with stairs) are unused.
In 2026, Metro plans to begin phasing out the original SD-400 cars and to refurbish the SD-460 cars for continued use. In May 2023, Metro received a $196.2 million federal grant to purchase up to 48 Siemens S200 high-floor light rail vehicles to replace 25 of the oldest cars. Six months later, Bi-State's board approved a contract with Siemens Mobility worth up to $390.4 million for as many as 55 new light rail vehicles.
Metro operates two storage and maintenance facilities. Ewing Yard sits between the Grand and Union Station stops just west of downtown St. Louis; 29th Street Yard is located between the JJK Center and Washington Park stops in East St. Louis.
Roster
Unit Type | Year Built | Quantity | Numbers |
---|---|---|---|
Siemens SD400 | 1991–1993 | 31 | 1001–1031 |
Siemens SD460 | 1999 | 10 | 2001–2010 |
2000 | 24 | 3001–3024 | |
2004–2005 | 22 | 4001–4022 | |
Siemens S200 | Deliveries to begin in 2027 |
Fares
MetroLink uses a proof-of-payment system. Tickets can be purchased at ticket-vending machines at the entrance to all stations and must be validated before boarding the train. Single-ride tickets are good for up to two hours in the direction that a passenger initially boards. Some fares, such as monthly or weekly fares, do not need to be validated, but passengers must have the pass in their possession while riding and must show the pass to security personnel upon request. Reduced fares can be purchased by seniors ages 65+, people with disabilities, and children ages 5–12. Up to three children under 5 may ride free with a fare-paying rider. Proof of age may be requested of all people riding with reduced fares. Other types of passes include a Semester Pass for full-time students.
In 2018, Metro introduced the Gateway Card, a multi-use smart card that was intended to eliminate most paper passes and tickets. In 2023, Metro announced that it would replace the Gateway Card—one Bi-State official called it a "failed system"—with a new fare collection system as part of the Secure Platform Plan.
MetroLink Fare Structure | ||
---|---|---|
Metro Fare Type | Mode | Current Fare |
Cash Base Fare | Rail | $2.50 |
Cash (Reduced Fare)* | Rail | $1.25 |
2-Hour Pass/Transfer | Bus/Rail | $3.00 |
2-Hour Pass/Transfer (Reduced Fare)* | Bus/Rail | $1.50 |
2-Hour Pass (from Lambert Airport) | Bus/Rail | $4.00 |
(10) 2-Hour Passes | Bus/Rail | $30.00 |
One-Day Adventure Pass | Bus/Rail | $5.00 |
Weekly Pass | Bus/Rail | $27.00 |
Monthly Pass | Bus/Rail | $78.00 |
Monthly Pass (Reduced Fare)* | Bus/Rail | $39.00 |
Combo Pass | Bus/Rail | $98.00 |
University Semester Pass | Bus/Rail | $175.00 |
* Reduced fares require a Metro reduced fare permit
† Two-hour passes can only be purchased as a mobile fare option on the Transit app |
Projects in progress
MidAmerica Airport extension
In 2019, the St. Clair County Transit District was awarded $96 million in Illinois infrastructure funding to build a 5.2-mile (8.4 km) extension of the Red Line from Shiloh–Scott to MidAmerica St. Louis Airport in Mascoutah. This extension will include two 2.6-mile (4.2 km) segments, a double-track and a single-track segment, along with a station at the airport. Construction on the extension began in 2023 with Metro expecting completion in the spring of 2026.
System rehabilitation
In 2023, Metro began a system-wide rehabilitation program that will last several years. That spring, Metro began rehabilitating the downtown subway tunnels, including the Laclede's Landing, Convention Center, and 8th & Pinestations. Elsewhere, catenary wire, curve tracks, platforms, retaining walls, staircases, and system conduit are to be upgraded or replaced.
Beginning in 2025, Metro will start rehabilitating the Union Station tunnel with rehabilitation of the Cross County tunnels beginning in 2026. The latter will include the renovation of the Skinker and University City–Big Bend subway stations and the construction of a storage siding near the Richmond Heights station. In 2026, Metro expects to complete upgrades to the Supervisory Control Automated Data Acquisition (SCADA) and Public Address/Customer Information (PA/CIS) systems. The upgraded SCADA/PA/CIS will operate as an integrated system that monitors and controls operations and will allow Metro to provide real-time arrival information to passengers, such as live displays at stations.
Secure Platform Plan
In 2024, Metro Transit began adding turnstiles at all MetroLink stations as part of its $52 million Secure Platform Plan (SPP). Stations will also receive a new fare collection system, more fences, passenger-assist telephones, and more than 1,800 cameras to be monitored at a center opened in November 2022 at Metro's Central Garage.
The SPP will be implemented in three "packages" with full operation expected to begin in 2026. In September 2023, Bi-State awarded a $6.4 million contract to Millstone Weber LLC for the first package covering four Illinois stations.The gates at these first four stations began operating in September 2024. However, due to delays in implementing a new fare collection system, Metro staff will operate the fare gates manually at first. The second package covers seven Missouri stations and is also slated for completion by early 2025. The remaining stations and the upgraded fare collection system are expected to be operational by early 2026.
Projects in planning
North-South expansion
MetroLink's proposed North-South light rail line would lack the rapid transit-like characteristics of the Red and Blue lines, resembling instead other U.S. on-street light rail lines, such as those in Houston or Phoenix. The new line has been named the Green Line and would connect to the Red and Blue lines with an infill transfer station.
This 5.6-mile (9.0 km) line would serve about 10 stations between Chippewa Street in South St. Louis and Grand Boulevard in North St. Louis running primarily on Jefferson Avenue. It would provide a fixed rail upgrade to Metro's #11 (Chippewa) and #4 (Natural Bridge) bus routes. In September 2023, Bi-State Development's board approved a 4-year, $18.9 million contract with the joint venture Northside-Southside Transit Partners to provide consulting services for the design phase of the project. In February 2024, the East-West Gateway Council of Governments approved the updated locally preferred alternative along Jefferson. The 2023 design study estimates 5,000 daily boardings, $8-9 million in annual operating costs, and $1.1 billion in capital costs.
An extension of the Green Line into North St. Louis County had been explored. In 2023, four alternatives were proposed that would have continued the line from the Grand/Fairground station along Natural Bridge Avenue toward the county. By 2024, County leadership had rejected all four routes primarily due to the unfunded 3-mile (4.8 km) gap between the Grand/Fairground station and the county line. Additionally, concerns were raised about federal funding, ridership, right-of-way constraints and other factors. Instead, county leaders are exploring alternatives for North County such as light rail branching off the existing Red Line near the University of Missouri–St. Louis, rapid bus service or a hybrid of the four 2023 alternatives.
Previous proposals
These extensions were proposed between the year 2000 and in 2010 when Metro released its 30-year long range plan, Moving Transit Forward. Most are defunct; regional leaders have said their priorities are the proposed extensions in the city of St. Louis and North St. Louis County.
North-South
- Northside/Southside 2008. This 21–29-mile (34–47 km) expansion was planned in two separate locally preferred alternatives (LPA). In 2008 a 12-mile (19 km) Northside LPA was selected that would have traveled between downtown St. Louis and St. Louis Community College-Florissant Valley via North City and County. That same year, a 9–17-mile (14–27 km) Southside LPA was selected that would have traveled between downtown St. Louis and Bayless Avenue via South City and County.
- Northside/Southside 2018. In 2018, a updated Northside/Southside LPA was approved that shortened the expansion to an approximately 8-mile (13 km) alignment between Grand in North St. Louis and Chippewa in South St. Louis via a loop on 9th and 10th streets in downtown St. Louis. See Projects in planning section for updates on Northside/Southside as of 2024.
Cross County
- MetroSouth. This 6–12-mile (9.7–19.3 km) extension was envisioned as Cross County Segment 2 and would have extended the current Blue Line from its terminus in Shrewsbury further south beyond Interstates 270/255 to Butler Hill Road. A third alternative would have ended at Watson Road. An environmental impact study was completed in 2004; however, selection of an LPA was deferred due to the lack of local funding sources as well as other factors.
- MetroNorth. This approximately 12-mile (19 km) extension was envisioned as Cross County Segment 3 and would have extended the current Blue Line from Clayton towards Florissant, Missouri. Some of this segment would have followed the former Terminal Railroad Association of St. Louis' Central Belt right-of-way paralleling Interstate 170.
- Daniel Boone. This 8–10-mile (13–16 km) extension would have branched off the Cross County corridor near Olive Boulevard along disused Rock Island Railroad right-of-way. It would then turn west and follow existing trackage operated by Central Midland Railway to Page Avenue where the line would continue to Westport Plaza. An approximately 12-mile (19 km) extension to Chesterfield would have been a potential Phase 2 of the Daniel Boone branch. The alignment would have continued west following Page Avenue and Highway 364 then turning towards Creve Coeur Lake Memorial Park. From there it would have headed to Spirit of St. Louis Airport in the Chesterfield Valley. This alignment has not been given serious consideration because of its perceived low ridership potential.
St. Charles County
- A plan to expand MetroLink 16–20 miles (26–32 km) from St. Louis Lambert International Airport northwest to St. Charles County was abandoned after St. Charles County voters twice rejected a sales tax for the extension in 1996; subsequently, all MetroBus service was ended. Had the extension been funded, the route would have used the Old St. Charles Bridge (now demolished) over the Missouri River to access the county.
Madison County
- In 2005, a study was performed to analyze extending MetroLink into Madison County, Illinois. The study recommended two alignments that would have begun near the 5th & Missouri station in East St. Louis then continue through Granite City, Collinsville, Wood River, and Glen Carbon between 21–23 miles (34–37 km) away. The alignment would have split in Madison, Illinois with one branch ending in Alton and the other in Edwardsville. In order to execute any Madison County extensions, Metro would have to collaborate with Madison County Transit.
Station gallery
See also
References
- ^ "Transit Ridership Report Third Quarter 2024" (PDF). American Public Transportation Association. November 20, 2024. Retrieved November 23, 2024.
- ^ "Transit Ridership Report Fourth Quarter 2023" (PDF). American Public Transportation Association. March 4, 2024. Retrieved September 5, 2024.
- ^ "History – The 1990s – MetroLink". Bi-State Development Agency (Metro). 2010. Archived from the original on August 23, 2013. Retrieved August 11, 2013.
- ^ "Procurement Information". Bi-State Development Agency (Metro). 2010. Archived from the original on August 18, 2013. Retrieved August 11, 2013.
- ^ St.Louis Metro Link Project, Final Environmental Impact Statement. U.S. Department of Transportation Urban Mass Transportation Administration, East-West Gateway Coordinating Council. October 9, 1987. pp. 2–26. Retrieved December 10, 2018.
- ^ "A Lesson for Jacksonville: The St. Louis Metrolink". Metro Jacksonville. April 9, 2009. Archived from the original on December 14, 2018. Retrieved December 10, 2018.
- ^ "World Systems List index". LRTA. Archived from the original on October 27, 2019.
- ^ "Rapid Transit Database". Institute for Transportation and Development Policy. ITDP. October 11, 2020. Archived from the original on October 7, 2024. Retrieved November 24, 2024.
- ^ "Fare Increase 2014". Metrostlouis.org. Archived from the original on April 16, 2016. Retrieved April 10, 2016.
- ^ Track Design Handbook for Light Rail Transit. Transportation Research Board. 2012. ISBN 978-0-309-25824-1.
This draws a line between the St. Louis example above and a light metro rail operation ...
- ^ "Joint International Light Rail Conference" (PDF). Onlinepubs.trb.org. p. 671. Archived (PDF) from the original on May 25, 2013. Retrieved July 25, 2022.
Except for these few grade crossings, the MetroLink project would be rail rapid transit rather than light rail.
- ^ "History". Metro Transit – Saint Louis. Archived from the original on September 14, 2023. Retrieved November 7, 2023.
- ^ "World.nycsubway.org: St. Louis, Missouri". Nycsubway.org. Archived from the original on April 17, 2016. Retrieved April 10, 2016.
- ^ Tipton, Virgil (June 22, 1994). "Takeoff: MetroLink Opens Lambert Stop Saturday". St. Louis Post-Dispatch.
- ^ "UrbanRail.Net > North America > USA > Missouri > St. Louis Metrolink". www.urbanrail.net. Archived from the original on October 1, 2023. Retrieved September 14, 2023.
- ^ "Soon-to-open Cortex MetroLink Station is more than just another stop, say regional transit leaders". STLPR. Archived from the original on October 1, 2023. Retrieved September 14, 2023.
- ^ "Metro – Inside MetroLink". Metro. Archived from the original on September 11, 2008. Retrieved October 23, 2007.
- ^ "Metro Announces August 26 Grand Opening Date for Cross County MetroLink Extension" (PDF) (Press release). Metro. August 7, 2006. Archived from the original (PDF) on October 9, 2007. Retrieved June 7, 2007.
- ^ American, Jessica Bassett Of the St Louis (December 6, 2007). "Metro loses suit against Cross County Collaborative". St. Louis American. Archived from the original on September 26, 2023. Retrieved September 26, 2023.
- ^ "MetroLink gets creative in opening first new station in more than a decade". Ksdk.com. July 31, 2018. Archived from the original on May 27, 2022. Retrieved July 25, 2022.
- ^ "MetroLink Saw Record Number of Boardings on Stanley Cup Championship Parade and Rally Day". Metro Transit – Saint Louis. Archived from the original on December 13, 2024. Retrieved December 11, 2024.
- ^ "Blues fans set a record for MetroLink numbers". ksdk.com. June 18, 2019. Retrieved December 11, 2024.
- ^ Lindsey (August 16, 2022). "MetroLink Flood Damage Update". metrostlouis.org. Archived from the original on September 12, 2022. Retrieved September 12, 2022.
- ^ Schrappen, Colleen (August 21, 2022). "MetroLink to resume full service, but cost for flood repairs could double". STLtoday.com. Archived from the original on September 12, 2022. Retrieved September 12, 2022.
- ^ Wanek-Libman, Mischa (July 29, 2022). "Metro St. Louis estimates flood damage between $18-$20 million". Mass Transit. Archived from the original on February 19, 2024. Retrieved February 19, 2024.
- ^ Jerry (September 1, 2022). "MetroLink Changes Starting September 5: Blue Line Service to Operate Between Shrewsbury and Forest Park". Metro Transit – Saint Louis. Archived from the original on September 25, 2022. Retrieved March 18, 2024.
- ^ Schlinkmann, Mark (August 1, 2023). "Metro gets nearly $28 million in federal aid to cover repairs after 2022 flood". STLtoday.com. Archived from the original on September 5, 2023. Retrieved September 5, 2023.
- ^ "Upcoming Schedule Changes". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved March 18, 2024.
- ^ Vallely, Jerry (March 24, 2023). "Memorandum of Understanding Approved for Bi-State Development Team to Plan, Design and Develop Jefferson Alignment MetroLink Expansion". BSD. Archived from the original on September 14, 2023. Retrieved September 12, 2023.
- ^ Schlinkmann, Mark (May 5, 2023). "Feds give Metro $196 million grant for new MetroLink cars". STLtoday.com. Archived from the original on February 25, 2024. Retrieved May 17, 2023.
- ^ Schlinkmann, Mark (November 29, 2023). "Bi-State board OKs $390 million contract for new MetroLink cars". STLtoday.com. Archived from the original on February 5, 2024. Retrieved February 5, 2024.
- ^ "Light Rail Vehicle (LRV) Replacement". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved November 28, 2024.
- ^ "UrbanRail.Net > North America > USA > Missouri > St. Louis Metrolink". Urbanrail.net. Archived from the original on March 10, 2018. Retrieved April 10, 2016.
- ^ "St. Louis Metro to Launch MetroLink Extension August 26". Apta.com. Archived from the original on February 2, 2017. Retrieved April 10, 2016.
- ^ Hemphill, Evie. "Soon-to-open Cortex MetroLink Station is more than just another stop, say regional transit leaders". news.stlpublicradio.org. Archived from the original on June 17, 2019. Retrieved June 17, 2019.
- ^ "UrbanRail.Net > North America > USA > Missouri > St. Louis Metrolink". www.urbanrail.net. Archived from the original on October 1, 2023. Retrieved December 10, 2024.
- ^ "MetroLink Schematic Map" (PDF). Metro St. Louis. Archived (PDF) from the original on February 27, 2021. Retrieved September 26, 2022.
- ^ "MetroLink Schematic Map" (PDF). Metro St. Louis. Archived (PDF) from the original on February 27, 2021. Retrieved September 26, 2022.
- ^ "Siemens AG – Projects – Rolling Stock". Siemens. Archived from the original on February 7, 2007. Retrieved January 23, 2007.
- ^ "SD460 High-Floor Light Rail Vehicle – St. Louis, Missouri" (PDF). Siemens. Archived from the original (PDF) on February 10, 2015. Retrieved February 10, 2015.
- ^ "The St. Louis Streetcar and MetroLink: Compatibility Issues to Address Before Expansion". nextSTL. March 15, 2013. Archived from the original on May 5, 2016. Retrieved April 10, 2016.
- ^ "@MetroSTL". Twitter. July 26, 2021. Archived from the original on July 26, 2021. Retrieved July 27, 2021.
- ^ Schlinkmann, Mark (May 5, 2023). "Feds give Metro $196 million grant for new MetroLink cars". STLtoday.com. Archived from the original on February 25, 2024. Retrieved May 17, 2023.
- ^ Schlinkmann, Mark (November 29, 2023). "Bi-State board OKs $390 million contract for new MetroLink cars". STLtoday.com. Archived from the original on February 5, 2024. Retrieved February 5, 2024.
- ^ "Modern Urban Rail Systems". Bi-State Transit Info & Roster. Archived from the original on August 19, 2012.
- ^ Equipment Railway Age January 1990 page 8
- ^ "Fare Chart". Metro. Archived from the original on July 2, 2014. Retrieved June 1, 2014.
- ^ Schlinkmann, Mark (February 7, 2023). "Metro Transit replacing 'failed' $10.3 million smart card system". STLtoday.com. Archived from the original on October 2, 2023. Retrieved September 25, 2023.
- ^ "Fares & Passes". Metro Transit – Saint Louis. Archived from the original on February 17, 2024. Retrieved February 17, 2024.
- ^ Schlinkmann, Mark (June 14, 2019). "Illinois to pay for long-sought MetroLink extension to MidAmerica Airport". STLtoday.com. Archived from the original on November 2, 2021. Retrieved September 20, 2022.
- ^ "Trajectory for Transit in 2022 Points to Need for Continued Collaboration". January 19, 2022. Archived from the original on February 3, 2022. Retrieved February 2, 2022.
- ^ "When will MetroLink extension to MidAmerica Airport be complete? How much will it cost? - MidAmerica St. Louis Airport (BLV) | Mascoutah, IL". flymidamerica.com. July 14, 2021. Archived from the original on September 20, 2022. Retrieved September 20, 2022.
- ^ Cella, Kim (November 1, 2023). "Construction Underway on MetroLink Extension Project in St. Clair County". St. Clair County Transit District. Archived from the original on November 7, 2023. Retrieved November 7, 2023.
- ^ Bauer, Will (December 28, 2023). "Construction underway on 5-mile MetroLink extension from Scott AFB to MidAmerica Airport". STLPR. Archived from the original on February 4, 2024. Retrieved February 4, 2024.
- ^ "Infrastructure Projects". Metro Transit – Saint Louis. Retrieved November 28, 2024.
- ^ "Downtown Tunnel Repairs and Fire Suppression Upgrades". Metro Transit – Saint Louis. Archived from the original on December 13, 2024. Retrieved November 28, 2024.
- ^ "8th & Pine Station Enhancement Project". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved November 28, 2024.
- ^ "Convention Center Enhancement Project". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved November 28, 2024.
- ^ "MetroLink | General Maintenance". Metro Transit – Saint Louis. Archived from the original on December 3, 2024. Retrieved November 28, 2024.
- ^ "Union Station Tunnel Rehabilitation". Metro Transit – Saint Louis. Archived from the original on December 13, 2024. Retrieved November 28, 2024.
- ^ "Cross County Tunnel Remediation". Metro Transit – Saint Louis. Archived from the original on December 7, 2024. Retrieved November 28, 2024.
- ^ "Richmond Heights Turnout". Metro Transit – Saint Louis. Archived from the original on December 7, 2024. Retrieved November 28, 2024.
- ^ "MetroLink Software Enhancements". Metro Transit – Saint Louis. Archived from the original on December 1, 2024. Retrieved November 28, 2024.
- ^ "New MetroLink Customer Information System". Metro Transit – Saint Louis. Retrieved November 28, 2024.
- ^ "New Fare Collection System". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved November 28, 2024.
- ^ "Secure Platform Plan Project". Metro Transit – Saint Louis. Archived from the original on September 25, 2023. Retrieved September 15, 2023.
- ^ Fenske, Sarah (October 17, 2024). "MetroLink gates are up, but fare cards to open them won't be ready for a year". www.stlmag.com. Archived from the original on December 7, 2024. Retrieved November 18, 2024.
- ^ Jerry (September 26, 2023). "Contract Awarded for First Construction Package of MetroLink's Secure Platform Plan". Metro Transit – Saint Louis. Archived from the original on September 26, 2023. Retrieved September 26, 2023.
- ^ "St. Louis Metro installs MetroLink security gates to access station platform at Emerson Park MetroLink Station". Mass Transit. September 12, 2024. Archived from the original on November 17, 2024. Retrieved November 18, 2024.
- ^ "Secure Platform Plan – Phase I". Metro Transit – Saint Louis. Retrieved November 28, 2024.
- ^ "Secure Platform Plan – Phase II". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved November 28, 2024.
- ^ "Secure Platform Plan – Phase III". Metro Transit – Saint Louis. Archived from the original on December 14, 2024. Retrieved November 28, 2024.
- ^ "About". St. Louis MetroLink Green Line. Archived from the original on December 13, 2024. Retrieved December 11, 2024.
- ^ "Claiming It Would "Divide Us", Stenger Opposes North-South Rail Transit – NextSTL". June 20, 2016. Archived from the original on November 8, 2020. Retrieved September 12, 2023.
- ^ "Northside-Southside TAA" (PDF). East-West Gateway Council of Governments. Aecom. Archived (PDF) from the original on September 11, 2022. Retrieved September 12, 2023.
- ^ "Northside-Southside TAA" (PDF). East-West Gateway Council of Governments. Aecom. Archived (PDF) from the original on September 11, 2022. Retrieved September 12, 2023.
- ^ "Board of Commissioners 9/22/23" (PDF). Bi-State Development Agency. pp. 196–197. Archived (PDF) from the original on September 26, 2023. Retrieved September 26, 2023.
- ^ Cella, Kim (February 28, 2024). "East-West Board Adopts Jefferson Ave. Alignment as the Locally Preferred Alternative for Light Rail Expansion in Northside-Southside Corridor". Citizens For Modern Transit. Archived from the original on February 28, 2024. Retrieved February 28, 2024.
- ^ Schlinkmann, Mark (February 18, 2023). "Bi-State reveals possible North County MetroLink routes". STLtoday.com. Archived from the original on September 29, 2023. Retrieved September 12, 2023.
- ^ Schlinkmann, Mark (June 6, 2024). "New St. Louis MetroLink line connecting to North County may not happen". STLtoday.com. Archived from the original on November 30, 2024. Retrieved November 18, 2024.
- ^ "Moving Transit Forward" (PDF). Metro Transit. Archived (PDF) from the original on October 13, 2022. Retrieved September 11, 2022.
- ^ Schlinkmann, Mark (November 17, 2021). "St. Louis County back in picture for north-south MetroLink expansion". STLtoday.com. Archived from the original on September 11, 2022. Retrieved September 11, 2022.
- ^ "MetroLink Planning – Northside". East-West Gateway. Archived from the original on August 3, 2008. Retrieved October 30, 2008.
- ^ "MetroLink Planning – Southside". East-West Gateway. Archived from the original on March 26, 2009. Retrieved October 30, 2008.
- ^ "Northside-Southside Executive Summary" (PDF). East-West Gateway Council of Governments. Archived (PDF) from the original on March 12, 2024. Retrieved March 12, 2024.
- ^ "St. Louis Metro South MetroLink Extension: DEIS" (PDF). East-West Gateway Council of Governments. November 1, 2005. p. 2-19. Archived (PDF) from the original on March 12, 2024. Retrieved March 12, 2024.
- ^ "East-West Gateway Board Defers Selection of MetroLink Alternative for Metro South Study Area" (PDF). East-West Gateway. November 3, 2004. Archived from the original (PDF) on May 15, 2013. Retrieved September 29, 2010.
- ^ "LPAs for Daniel Boone, Northside and Southside Study Areas" (PDF). East-West Gateway Council of Governments. Archived from the original (PDF) on April 3, 2019. Retrieved September 25, 2022.
- ^ "MetroLink Planning – Daniel Boone". East-West Gateway. Archived from the original on March 20, 2007. Retrieved June 1, 2007.
- ^ "St. Louis RR Maps". Railsandtrails.com. Archived from the original on June 29, 2022. Retrieved July 25, 2022.
- ^ Uptergrove, Kate (July 7, 2015). "St. Louis County to explore MetroLink expansion; St. Charles County says no". MidRiversNewsMagazine.com. Archived from the original on September 25, 2022. Retrieved November 7, 2023.
- ^ "Madison County Light Rail Feasibility Study Final Report" (PDF). East-West Gateway Council of Governments. Archived (PDF) from the original on September 25, 2022. Retrieved September 25, 2022.
External links
- Metro – Official website for Metro Transit
- Bi-State Development – Official website for Bi-State Development
- St. Clair County Transit District – Official website for the St. Clair County Transit District
- Citizens for Modern Transit – St. Louis transit advocacy group
- Arts in Transit Website