NP Kunta Ultra Mega Solar Park
The first phase of the park was commissioned on 9 May 2016 with a capacity of 200 MW. An additional 50 MW capacity was commissioned on 29 July 2016. A further 750 MW was planned to have been commissioned by March 2018 in the second phase.
In August 2016, Tata Power Solar commissioned a 100 MW solar project at the park built over an area of 200 hectares (500 acres). This was the largest solar project commissioned using domestically manufactured solar cells and modules at the time.
In May 2018, Azure Power commissioned a 50 MW solar capacity at the park. In July 2018, Tata Power commissioned another 100 MW capacity, taking total commissioned capacity to 500 MW.
In July 2018, 750 MW were awarded for installation at ₹2.71/kW⋅h.
As of 30 April 2021, 978.5 MW capacity was commissioned by the following companies: Sprng Agnitra (250 MW), Ayana Solar (228.5 MW), SB Energy Solar (250 MW) and NTPC (250 MW). Another 400 MW was installed by Tatas (100 MW), ACME (150 MW), Azure (50 MW) and FRV Ltd (100 MW) at adjacent Galiveedu Solar Park which is not part of NP Kunta Solar Park.
See also
References
- ^ "Power generation begins at Kunta ultra mega solar project | Business Standard News". Business-standard.com. Retrieved 14 September 2016.
- ^ "India Solar Resource - Global Horizontal Irradiance - Annual Average, by NREL, National Renewable Energy Laboratory".
- ^ "Status of Renewable Energy projects in Andhra Pradesh" (PDF). Retrieved 10 May 2021.