Rukungiri–Kihihi–Ishasha–Kanungu Road

Rukungiri–Kihihi–Ishasha–Kanungu Road is a road in southwestern Uganda, connecting the town of Rukungiri in Rukungiri District and the town of Ishasha in Kanungu District, at the International border between Uganda and the Democratic Republic of the Congo. A spur of the road runs south from Kihihi to Kanungu.

Location

The Rukungiri–Kihihi–Ishasha–Kanungu Road starts at Rukungiri, running in a general westward direction. It passes through Kihihi, ending at Ishasha, at the border with DRCongo. A spur of the road runs in a general southern direction from Kihihi to Kanungu. The entire road distance is approximately 79 kilometres (49 mi) with the Rukungiri–Ishasha section measuring 52 kilometres (32 mi) and the Kihihi–Kanungu section measuring 27 kilometres (17 mi). The coordinates of the road near Kihihi in Kanungu District are:0°44'56.0"S, 29°41'53.0"E (Latitude:-0.748889; Longitude:29.698056).

Conversion to bitumen surface

Kabale, Kisoro, Kanungu
Kabale, Kisoro, Kanungu

The road, whose total length is 79 kilometres (49 mi), is presently made of unsealed gravel surface. In 2014, the government of Uganda obtained a US$109 million loan to upgrade this and other roads to bituminous surface. As of November 2014, procurement for a contractor was ongoing.

Landmarks

The following landmarks lie close or near the Rukungiri–Kihihi–Ishasha–Kanungu Road:

  • The town of Rukungiri in Rukungiri District, the location of the district headquarters.
  • The town of Kihihi in Kanungu District.
  • The town of Ishasha, at the International border with DRCongo.
  • Queen Elizabeth National Park. The road forms the southern border of the park, in the section between Kihihi and Ishasha.
  • The southern spur ends at Kanungu, the location of the headquarters of Kanungu District.

Construction

The construction contract was awarded to China Henan International Construction Company (CHICO), at a contract price of USh:207,834,646,967 (approx. US$57 million). The supervising engineering contract was awarded to SMEC International Pty Limited of Australia. The civil works contract was signed on 17 September 2018. Permission to start work was given on 5 November 2018. Completion is expected during the first quarter of 2022. The project is co-funded by the African Development Bank and the Government of Uganda.

As of 20 May 2021, progress of work was estimated at 41.16 percent, according to the Uganda National Roads Authority. Completion is still anticipated during the first half of 2022.

See also

References

  1. ^ Shem Oirere (3 October 2014). "Two New Road Links Will Help Boost Uganda's Economy". Dartford, United Kingdom: Worldhighways.com. Retrieved 11 September 2020.
  2. ^ Lam Kajubi; et al. (11 October 2013). "Environmental And Social Assessment: Resettlement Action Plan (RAP) of Proposed Upgrading Rukungiri–Kihihi–Ishasha/Kanungu Road to Bituminous Standards" (PDF). African Development Bank. Retrieved 11 September 2020.
  3. ^ "Location of Rukungiri–Kihihi–Ishasha–Kanugu Road At Google Maps" (Map). Google Maps. Retrieved 11 September 2020.
  4. ^ New Vision (4 March 2014). "AfDB To Finance Rukungiri-Ishaka Road Upgrade". New Vision. Kampala. Retrieved 11 September 2020.
  5. ^ URN Editorial (24 May 2014). "Government Secures Funds for Rukungiri - Kanungu Road". Kampala: Uganda Radio Network (URN). Retrieved 11 September 2020.
  6. ^ Sunrise Uganda (4 November 2014). "UNRA To Begin Works On 16 Roads Next Year". Kampala: Sunrise Uganda. Retrieved 11 September 2020.
  7. ^ Uganda National Roads Authority (27 June 2019). "Project Profile: Rukungiri-Kihihi-Ishasha/Kanungu (78.5 km)". Kampala: Uganda National Roads Authority. Retrieved 11 September 2020.
  8. ^ Elizabeth Kusasira (20 May 2021). "Rukungiri–Kihihi–Ishasha–Kanungu Road (78.5KM) Works Progress At 41.16 Percent". Uganda National Roads Authority. Kampala, Uganda. Retrieved 26 August 2021.


00°44′56″S 29°41′53″E / 0.74889°S 29.69806°E / -0.74889; 29.69806