Scollay Square (BERy Station)
The station was closed on March 22, 2014 for a major renovation, which included retrofitting the station for accessibility and building a new glass headhouse on City Hall Plaza. The new fully accessible station was reopened on March 21, 2016.
History
Scollay Square
As the first horsecar lines were built in the late 1850s, the Scollay Building in Scollay Square became the transfer point between the various lines. The Metropolitan Railroad, the largest of the horsecar systems, used the Tremont House hotel a block to the south of Scollay Square as a terminus for many routes.
The northern section of the Tremont Street Subway opened on September 3, 1898, with a station at Scollay Square. The station had an unusual platform design. The three-sided main platform served northbound and southbound through tracks plus the Brattle Loop track, one of two turnback points (along with Adams Square) for streetcars entering the subway from the north; a side platform also served the loop Boston Elevated Railway (BERy) streetcars from Everett, Medford, and Malden (which formerly ran to Scollay Square on the surface) used Brattle Loop, as did cars from Lynn and Boston Railroad and its successors. The last of those, the Eastern Massachusetts Street Railway, used the loop until 1935.
Scollay Square and Adams Square had similar baroque headhouses with four-sided clock towers. Unlike Adams Square, the Scollay Square headhouse had its entrance at one end of the structure. A small exit structure was located to the north, while the Brattle Loop used a separate entrance built into a building at Court Street and Brattle Street. The headhouses of the Tremont were sharply criticized as "pretentiously monumental", with the Scollay Square headhouse compared to "an enlarged soda fountain". Later stations on the East Boston Tunnel and Washington Street Tunnel incorporated this criticism into their more modest headhouses.
On June 10, 1901, Main Line Elevated trains began using the through tracks through the Tremont Street Subway, while streetcars continued using the Brattle Loop. The main platform was divided into separate sections for northbound and southbound elevated trains, each with separate staircases and ticket takers, with sliding platform sections to meet the high-level doors on the El cars. Passages under the Brattle Loop were built from each side to the Brattle Loop platform, which had its own staircases and ticket takers for streetcars. On July 9, 1904, streetcar passengers began paying fares to the streetcar conductors and the streetcar ticket office was repurposed for southbound El passengers.
Court Street
On December 30, 1904, the East Boston Tunnel opened for streetcars from Maverick Square in East Boston to a one-track stub-end terminal at Court Street next to Scollay Square. A passageway was built connecting the two stations. A bronze statue of John Winthrop was relocated from Scollay Square to the Back Bay in 1903 to make room for the exit stairs from the station. Erected in 1880, the statue had already been moved in 1898 to make room for the first headhouse.
The stub-end track at Court Street was normally restricted to one streetcar at a time; however, two were commonly allowed during peak periods. On October 6, 1906, a conductor was crushed to death between two streetcars while preparing his trolley pole for the return trip - the second such accident at the station. In addition to these incidents, the stub-end terminal was operationally inefficient, which prompted the need for a replacement.
Return to streetcar use
On November 30, 1908, Elevated trains moved into the parallel Washington Street Tunnel and the Tremont Street Subway through tracks returned to streetcar operations. The separated platform areas were kept; the through tracks offered a free transfer to East Boston Tunnel streetcars (plus a small toll for use of the tunnel, separate from normal BERy fares), while the Brattle Loop platform was kept separate for "foreign" (non-BERy) cars on a separate fare system.
Scollay Under
In November 1912, the Boston Transit Commission began an extension of the East Boston Tunnel west to Bowdoin. Court Street station was abandoned on November 15, 1914; a passageway was opened to connect Scollay Square station with Devonshire, which temporarily served as the terminal. The floor of the station was removed and the tunnel angled down through the former station to allow for the extended tunnel to proceed under the existing Scollay Square station. The upper part of the former station was later converted to storage space.
Scollay Under opened on March 13, 1916, with streetcars looping empty around the Bowdoin loop. It had an island platform with staircases to the existing Scollay station. The 1898-built platform was extended during the project to accommodate expected loads of transferring passengers. Bowdoin station opened on March 18. An Orient Heights–Central Square, Cambridge through service was started, while several Cambridge streetcar lines entered the new tunnel and terminated on a pocket track at Scollay Under.
The northbound (Cornhill Street) entrance was closed on November 24, 1917, forcing all passengers to use the southbound Tremont Row entrance. In 1927, the original headhouse was replaced with a simple staircase to improve sightlines for auto drivers. On April 18, 1924, the East Boston Tunnel including Scollay Under was converted from low-platform streetcars to high-platform third-rail-powered rapid transit. A portion of the low streetcar platform remained east of the new high platform.
The station was further renovated in 1928 with new lights, and improved fare collection equipment. Eastern Massachusetts Street Railway service to Brattle Loop ended on January 13, 1935, though some BERy streetcars continued to use it. The Metropolitan Transit Authority (MTA) replaced the BERy in 1947 and continued to reduce streetcar services. The last Brattle Loop service was discontinued in 1952. The northbound platform was extended over the loop in 1954 to allow two 3-car trains of PCC streetcars to board simultaneously.
Government Center
Boston City Hall Plaza replaced Scollay Square in the early 1960s. Scollay Square station was wholly renovated, and the northbound tunnel was realigned to accommodate the foundation of Boston City Hall. The work drastically altered the shape of Brattle Loop and provided a new northbound-to-southbound turnback loop. The stairways to the lower level were relocated, and a fare lobby was built in a low brick structure at the surface. The 1963-built headhouse was often described as resembling a bunker or a cave, even by MBTA management. Government Center station was dedicated on October 28, 1963, though the new loop was not activated until November 18, 1964, when the Commonwealth Avenue line was extended from Park Street to Government Center. Despite the new name, several tiles mosaics reading "Scollay Under" and "S" were still extant and gradually uncovered over the years.
On August 26, 1965, as part of a wholesale rebranding of the system, the MBTA (formed in 1964 to replace the MTA) designated the remaining streetcar routes as the Green Line and the East Boston Tunnel line as the Blue Line. In 1968-69, a "Phase I" modernization added false ceilings, fluorescent lights, and other aesthetic upgrades.
In the late 1970s, Mary Beams - an artist at Harvard's Carpenter Center for the Visual Arts - painted 19 murals which were placed along the wall behind the Brattle Loop. Although intended to be temporary, they received protective covers in the late 1980s and remained in good condition until the 2014 closure.
On February 11, 1983, the Green Line E branch was shut down by snow for several days; a Government Center-Lechmere shuttle ran in its stead - the first use of the Brattle Loop in three decades. Even after the E branch resumed operations several days later, the shuttle service ran until June 21, 1997. Since, the loop was used only for temporary car storage, largely during events at Boston Garden (later TD Garden) and after the morning peak.
Renovation
In 1990, the state agreed to a number of transit expansion and renovation projects to settle a lawsuit from the Conservation Law Foundation over the environmental impacts of the Big Dig. Due to its cost, complexity, and the need to completely shut down a major transfer station, Government Center was the last of 80 key stations to be upgraded for accessibility. Original plans in the 1990s called for the project to add two new entrances to the station, using the former west entrance to the Blue Line level and the former Brattle Loop entrance to the Green Line level. The Blue Line entrance would be close to Bowdoin station, allowing it to be closed.
The additional Green Line entrance was cut during preliminary design, but the Blue Line entrance was kept; until at least 2011, the MBTA still planned to close Bowdoin after Government Center was renovated. However, by 2013, the MBTA decided not to construct the planned west entrance at Government Center, and to instead build only a less-expensive emergency exit.
The main construction contract was awarded to Barletta Heavy Division in July 2013, and site preparation began in mid-November 2013. On March 22, 2014, Government Center station closed for two years for the reconstruction, which included new elevators, station entrance and lobbies, emergency exit-only structure on Cambridge Street between Court and Sudbury Street, escalators, LED signage, expanded fare collection area, upgraded back-up electrical power supply, improved interior finishes, station lighting, mechanical systems, and public address system. The abandoned side platform was almost completely tiled over. Additional vendor retail space was provided on both Green Line and Blue Line platforms. The platform levels feature terrazzo flooring color-coded to the lines.
During Government Center station's closure, Green Line trains passed through but did not stop at the station. For the duration of the closure, the B branch was cut back to Park Street (after the reopening of Government Center station, this would later be modified to keeping it at as the terminus permanently for five more years), while the D branch was cut to Park Street at rush hours and North Station at other times. The "C" and "E" branches kept their usual terminals. Bowdoin station was kept open for all MBTA operating hours (for the first time since 1981) during the closure. A shuttle bus, the 608 Haymarket via Government Center Loop route, operated in a loop from Haymarket station via State Street station, Government Center station, and Bowdoin station.
During the first two months of renovations, two additional Scollay Under tile signs were uncovered on the Blue Line level. After the first sign was discovered in April, the MBTA announced that it would be restored and placed in the renovated station, similar to previously found mosaics at South Station and Arlington. In total, five 'Scollay Under', one 'Scollay', and two single-letter mosaics were restored. An original faregate, ticket booth, and ceiling arches were also found. The 1970s Mary Beams murals - made of house paint on plywood - did not meet fire code for installation in the rebuilt station. Instead, they were sold at auction in October 2015, with the proceeds going to an enamel commemorative panel and new artworks placed in the new station.
By September 2014, demolition was completed and the steel frame of the new glass headhouse had been erected. At that point, the project was on schedule and on budget. In July 2015 the MBTA announced that the project was still on schedule for a Spring 2016 reopening. In August 2015, the MBTA revealed that the glass used on the headhouse was defective due to poor workmanship, with failed seals between the double-paned glass causing fogging. The glass was replaced at the contractor's expense and did not affect the project's schedule.
On February 2, 2016, the MBTA announced that the station would reopen on March 26, 2016 and that the project was within its budget. On February 19, the MBTA tested multicolored LED lights to illuminate the glass headhouse. After several unpublicized notices, the MBTA announced on March 9 that the station would open on March 21 instead, with a ceremony at 11:45am and full opening an hour later. On the radio command of Governor Charlie Baker, service to the station resumed at 12:43pm.
Design and engineering for the station cost $25 million; the MBTA estimated the construction cost would be $91 million. The primary construction contract was for $82 million, and total construction cost was $88 million. The new station headhouse design was heavily criticized in a monthly architectural review by the social commentator and critic James Howard Kunstler. The headhouse has also been criticized for blocking the view of Old North Church from Tremont Street.
Since the loop opened in 1964, Government Center has been a terminus for scheduled service on one or more branches except for the 2014–2016 closure, 1980–1982, and a short period in 1967. It was the terminus for D branch service from 2016 to October 24, 2021, when it became instead the terminus for B and C branch service as part of preparations for the 2022 opening of the Green Line Extension. Government Center was the northern terminus of the Green Line from August 22 to September 18, 2022; the closure of the northern section allowed for final integration of the Medford Branch, elimination of a speed restriction on the Lechmere Viaduct, demolition of the Government Center Garage, and other work.
References
- ^ Belcher, Jonathan. "Changes to Transit Service in the MBTA district" (PDF). Boston Street Railway Association.
- ^ Vaccaro, Adam (9 March 2016). "MBTA moves Government Center opening date to March 21". Boston Globe. Retrieved 9 March 2016.
- ^ "A Guide to Ridership Data". MassDOT/MBTA Office of Performance Management and Innovation. June 22, 2020. p. 87.
- ^ Moskowitz, Eric (21 March 2016). "Government Center reopens". Boston Globe. Retrieved 21 March 2016.
- ^ Brayley, Arthur W. (September 27, 1900). "Boston's Street Railways: No. 4". Boston Globe. p. 6 – via Newspapers.com.
- ^ The Boston Horse and Street Railroad Guide. Edward E. Clark. 1887 – via Internet Archive.
- ^ "Transit By Street-cars". Boston Globe. October 28, 1877. p. 1 – via Newspapers.com.
- ^ Clarke, Bradley H.; Cummings, O.R. (1997). Tremont Street Subway: A Century of Public Service. Boston Street Railway Association. ISBN 0938315048.
- ^ Boston Transit Commission (1898). Annual report of the Boston Transit Commission, for the year ending August 15, 1898 (Report). City of Boston. pp. 45–51 – via Internet Archive.
- ^ Coburn, Frederick W. (November 1910). "Rapid Transit and Civic Beauty". New Boston. Vol. 1, no. 7. pp. 307–314 – via Google Books.
- ^ Rettig, Polly M. (June 14, 1976). "NATIONAL REGISTER OF HISTORIC PLACES INVENTORY -- NOMINATION FORM: Tremont Street Subway". National Park Service.
- ^ Chasson, George Jr. (1987). Lonto, Arthur J. (ed.). "Boston's Main Line El: The Formative Years 1879-1908". Headlights. 49. Electric Railroader's Association.
- ^ Kruh, David (1999). Always Something Doing: Boston's Infamous Scollay Square. Northeastern University Press. pp. 39, 44-45. ISBN 1555534104.
- ^ Bacon, Edwin Monroe; Phillips, Leroy (1928). Boston; a guide book to the city and vicinity. Ginn and Company. pp. 19, 20 – via Internet Archive.
- ^ "Three Car Victims". Boston Globe. October 7, 1906. p. 1 – via Newspapers.com.
- ^ Cudahy, Brian J. (1972). Change at Park Street Under. Stephen Greene Press. p. 31. ISBN 0828901732. LCCN 72081531.
- ^ "Devonshire-St Terminal". The Boston Globe. November 14, 1914. p. 14 – via Newspapers.com.
- ^ Bierman, Noah (December 26, 2009). "Transit archeology: Tour of abandoned subway network offers a glimpse of how the T was built". Boston Globe.
- ^ "From Cambridge To East Boston". The Boston Globe. March 12, 1916. p. 4 – via Newspapers.com.
- ^ "Few Used New Bowdoin Sq Tunnel Immediately After its Opening". Boston Globe. March 18, 1916. p. 14 – via Newspapers.com.
- ^ "This Time in History". Rollsign. Vol. 54, no. 11/12. Boston Street Railway Association. November–December 2017. p. 15.
- ^ Belcher, Jonathan. "Remnants of Abandoned Stations, Tunnels, and Station Entrances found on the MBTA". NETransit. Archived from the original on 12 November 2007.
- ^ Weir, Richard (4 October 2010). "Redesign fits Government Center to a T". Boston Herald. Retrieved 3 August 2014.
- ^ Gay, Malcolm (17 September 2015). "MBTA tracks down artist who created iconic murals". Boston Globe. Retrieved 1 October 2015.
- ^ Ridership and Service Statistics (PDF) (13 ed.). Massachusetts Bay Transportation Authority. 2010. p. 2.6. Archived from the original (PDF) on August 13, 2011.
- ^ Blake, Andrew (March 20, 1994). "MBTA to begin $467 million Blue Line project". Boston Globe – via Newspapers.com. (second page)
- ^ Moskowitz, Eric (October 5, 2011). "MBTA board OK's millions for station improvements". Boston Globe.
- ^ "Government Center Station Reconstruction Project Green Line / Blue Line Project Briefing" (PDF). Massachusetts Bay Transportation Authority. March 13, 2013. Archived from the original (PDF) on April 30, 2013.
- ^ Dungca, Nicole (31 July 2015). "Is Government Center station still on track?". Boston Globe. Retrieved 11 August 2015.
- ^ "MBTA > Riding the T". Archived from the original on 2017-09-13. Retrieved 2014-01-20.
- ^ Powers, Martine (7 May 2014). "Second 'Scollay Under' sign found at Government Center". Boston Globe. Retrieved 9 May 2014.
- ^ Powers, Martine (7 April 2014). "'Scollay Under' sign uncovered at Government Center station". Boston Globe. Archived from the original on 8 April 2014. Retrieved 9 May 2014.
- ^ Crimaldi, Laura (21 September 2014). "Government Center T station to feature glass entryway". Boston Globe. Retrieved 22 September 2014.
- ^ Fiore, Rebecca (23 June 2015). "Scollay Square signs to remain after Government Center overhaul". Boston Globe. Retrieved 24 June 2015.
- ^ Deehan, Mike (24 August 2015). "MBTA: Green Line Somerville Extension Faces $1B Overrun; Gov't Center Glass Needs To Be Replaced". WGBH. Retrieved 25 August 2015.
- ^ Vaccaro, Adam (2 February 2016). "Government Center T station to reopen March 26". Boston Globe. Retrieved 3 February 2016.
- ^ Annear, Steve (19 February 2016). "MBTA tests lights at new Government Center Station". Boston Globe. Retrieved 19 February 2016.
- ^ Vaccaro, Adam (19 March 2016). "Why the MBTA shut down Government Center for 2 years". Boston Globe. Retrieved 21 March 2016.
- ^ Kunstler, James Howard (4 May 2015). "Eyesore of the Month". James Howard Kunstler. Retrieved 2015-05-05.
- ^ DeLuca, Nick (11 December 2014). "Here Lies a Plaque: You Can't See the Old North Church From This Spot Anymore". BostInno. Retrieved 23 March 2016.
- ^ DeCosta-Klipa, Nik (October 22, 2021). "A 'subtle' but permanent change is coming to the Green Line this weekend". Boston Globe. Retrieved October 24, 2021.
- ^ "Building A Better T: GLX Medford Branch to Open in Late November 2022; Shuttle Buses to Replace Green Line Service for Four Weeks between Government Center and Union Square beginning August 22" (Press release). Massachusetts Bay Transportation Authority. August 5, 2022.