Second Harbour Crossing, Auckland
Roughly a third of New Zealand's population live in the Auckland Region, and the harbour bisects the city between its CBD and the North Shore. The current Auckland Harbour Bridge, built in 1959, was widened significantly in 1969 but has long been at capacity during peak hours. Carrying both national north–south and local traffic, it is a significant choke point in New Zealand's road network. The alternative motorway route around the edge of the harbour is also near peak capacity despite widening programs, and is easily gridlocked if the bridge is closed due to an accident or adverse weather conditions. The current crossing's limitations are a major contributor to Auckland's wider traffic congestion issues and their accompanying economic impacts.
New crossings have been proposed repeatedly over the previous decades. Most recently, in 2023 the Labour government of Chris Hipkins announced plans for a new crossing—involving two new road tunnels and a single light rail tunnel—to begin construction in 2029. However, with Labour's loss in the 2023 General Election these proposals are under review by the new National-led government of Prime Minister Christopher Luxon.
Background
Proposals for a crossing over Waitematā Harbour first arose only a few decades after Auckland was founded by the British in 1840. In 1860, John Bell designed a drawbridge on floating pontoons that would have given cattle and pig farmers in the rural North Shore a more direct route for driving their livestock into the city. While the plan included tolls to pay for its construction, its estimated cost (£16,000) was considered too high. Further bridges were proposed in 1927 and 1929, while the earliest tunnel proposal—floated during discussions about extending the city's rail network—dates to 1920.
A Royal Commission in 1946 recommended a four-lane road bridge, but further modelling predicted that there would be a population boom in the North Shore after being connected to the CBD, necessitating at least six lanes for future-proofing. The Auckland Harbour Authority was established in 1951 to lobby for funding, seek tenders from architects and construction firms, and further develop the plans, which had now settled on a compromise five-lane bridge with two additional walking and cycling lanes. However, the National government, led by Prime Minister Sidney Holland, insisted that the total budget could not exceed $5 million. This led to a so-called "austerity" design of a four-lane bridge without pedestrian/cycling lanes at all. Construction began on the Auckland Harbour Bridge in 1954, and it opened in 1959, with toll booths in place until 1984.
Traffic was immediately higher than expected from its first day of opening. By 1969 it had become obvious that the bridge was too narrow and two additional lanes—known locally as the "Nippon clip-ons"—were added on each side, creating an eight-lane bridge. At the time, it was predicted that the increased capacity would last only until about 1985. Even with the clip-on sections and new traffic management in place, the Harbour Bridge was soon experiencing congestion during rush hours again. Proposals for a second bridge soon started to be discussed, such as one connecting from Meola Reef to Birkenhead, though the idea was abandoned in the 1970s after public outcry.
Studies into traffic patterns across the Auckland region consistently predicted that congestion would continue to get worse as the North Shore grew further and Auckland City became more densely settled, and pressure for another harbour crossing has grown in tandem with the city's growth in population. New Zealand also experiences regular earthquakes and volcanic eruptions, and having only one crossing, which could be disabled during a natural disaster, has been identified as an issue of national concern. However, the substantial cost of any new crossing, as well as the disruption to communities on both sides of the harbour during construction—the North Shore is now a densely-populated urban district, unlike when the original bridge was built—has repeatedly dissuaded governments from investing in any specific plan.
Instead, planners have tended to focus on shorter-term solutions which mitigate the urgency for a new crossing. For example, Auckland Council's 2011 ten-year transit plan review explicitly argued that transit proposals which avoid the need for a second harbour crossing altogether, or at the very least delay its necessity, should be prioritised. The most notable of these projects, the Western Ring Route—a combination of upgraded and new motorway sections skirting the western edge of the harbour and suburbs, to provide relief for traffic travelling between the North Shore and West Auckland—was completed in July 2017 with the opening of the Waterview Connection.
Opponents of any new crossing have also pointed to multiple traffic surveys which have found that the number of car trips across the existing bridge during peak times has remained relatively stable since the 1990s, as the feeder junctions and roads at either end of the bridge are also at capacity. New journeys have instead been made possible with investment in better public transport, and specifically bus routes—since the construction of the hugely successful Northern Busway, 50% of peak time passengers across the bridge are now carried by bus.
However, there are few further options for continuing to increase cross-harbour capacity without an entirely new bridge or tunnel. In 2017, Auckland Transport's projections indicated that the Northern Busway would reach maximum capacity in 2026, twenty years earlier than originally expected, and there would soon be overcrowding at Albany, Sunnynook and Akoranga stations. The only option for increasing capacity further on the route is for it to be converted into a light rail line, but with the existing bridge at its weight limit this will be impossible until a second crossing is built to carry the line across to the CBD. The number of trucks making north–south journeys across the bridge is also predicted to more than double by mid-century, further emphasising the impact of congestion on the bridge to New Zealand's wider economy.
The failure to provide pedestrian or cycle lanes on the original bridge has also meant that there is no foot route across the harbour. While Auckland Transport has long provided a number of ferry routes for passengers travelling from areas of the North Shore to the central Downtown Ferry Terminal near Waitematā Station in the CBD, the inconvenience of the ferries in terms of both time and expense has long been seen as dissuading many Aucklanders from switching to active modes of travel, which would further help ease road congestion. Auckland Transport's Transport Emissions Reduction Pathway, published in August 2022, reaffirmed that a new fixed crossing with pedestrian and cycling lanes is seen as an essential part of its longer-term plans.
Modern proposals
1996 report
Following a detailed scoping study undertaken in 1996, Transit New Zealand identified its preferred options for a new crossing – either a new bridge approximately 500m west of the bridge connecting to the North-Western Motorway (SH16) via a tunnel underneath Ponsonby and Grey Lynn, or a tunnel slightly to the east of the bridge connecting to the Central Motorway Junction via twin cut-and-cover tunnels under the western CBD / Victoria Park. A follow-up study in 2003 found that these proposals, if both built together, would cost the equivalent of $4.5 billion in 2022 dollars.
2006-2009 alignment studies
In 2006, Transit New Zealand consulted on a new 10-year plan, and included funding for another study into a second harbour road crossing. This included the possibility of landing a future tunnel underneath the Western Reclamation (now known as the Wynyard Quarter), with a connecting tunnel to south of Victoria Park. Costs were estimated at NZ$3 billion. A possible tunnel between Mechanics Bay and Northcote was also considered in the feasibility studies, but faced increasing criticism from local groups, and was seen as problematic due to the denser residential zones and geographic difficulties faced on such an alignment.
In December 2007, Transit New Zealand noted that more than 160 options had been narrowed down, and the final option—known as "option 2C"—was published in early 2008. It consisted of two new crossings, made of two tunnels each. The first possible alignment (approximately 4.5 km) would be a parallel link several hundred metres directly to the east of the existing bridge, while the second alignment (approximately 6.5 km) would start in the same general environs in the North Shore, but travel diagonally southeastwards to link up with the motorway at Grafton Gully, east of the Auckland CBD. The second option, due to the need to cross shipping lanes, would need to be a tunnel. It would also have possibly connected to the CBD via a side branch tunnel, for use by public transport only.
There were a number of reactions from local community and lobbying groups to the consultation. North Shore City noted that it preferred a tunnel option for aesthetic reasons, and for the option to convert it to light rail at a future stage. Commentators like Brian Rudman noted that it would make the most sense to keep the new crossing for public transport only, possibly to connect with a rail tunnel to Britomart Transport Centre (now known as Waitematā Station). This statement was largely supported by North Shore mayor George Wood, who noted that public transport provision on any new crossing (including the possibility for light rail or heavy rail to connect to Waitematā Station) had been part of North Shore Council's plans for many years.
In mid-2008, the Waitematā Harbour Crossing study group—a private lobbying group representing local companies—released their recommended option, which would have connected from the existing Esmonde and Onewa motorway interchanges on the North Shore side to Auckland CBD, reaching land in the southwestern part of the Wynyard Quarter (though the links would have continued as tunnels for some further distance, likely going under Victoria Park). The option, selected from several hundred considered alignments, involved four separate tunnels, two for motor vehicles and two for public transport, the demolition of Victoria Park Viaduct, and a new rail station in the Wynyard Quarter. The total costs were estimated at between NZ$3.7 to NZ$4.1 billion, and their study predicted that it would increase the number of journeys across the harbour by 80% by 2041, with 30% by public transport.
In mid-2009, Waka Kotahi NZ Transport Agency (NZTA)—the successor to Transit New Zealand—safeguarded the route so that further redevelopment on the Wynyard Quarter would not negatively affect the future tunnel. On 2 December 2009, NZTA announced that designations would be protected for the four-tunnel option, though funding to build them was not allocated in upcoming budgets, and no future date for construction was announced.
2007 "Anzac Centenary Bridge" alternative
During the public discussions in 2007, a group of local politicians and architects put forward a proposal to build a new, much larger bridge to the east of the existing bridge, and then demolish the latter. The new cantilever spar cable-stayed bridge, designed by the Jasmax architectural firm, would be built in time for the 100-year memorial of the Gallipoli landings in 1915.
The new bridge would be roughly 50% longer than the existing one and triple the capacity by including corridors for light rail, cyclists, and pedestrians as well as cars and buses. The designers argued that the new bridge would pay for itself by freeing up 35 hectares of land (and 3.3 km of shoreline) for redevelopment in some of the most sought-after Auckland locations, like Saint Mary's Bay, which were currently taken up by large motorway approaches. The proposed bridge would also be cheaper to operate, and unlike a tunnel, would not need emission vents.
In October 2009, the bridge option again surfaced with a group of backers suggesting that a bridge would be a better option from both urban design and transport planning perspectives. However, critics argued that the extra investment required to meet the tight 2015 deadline would necessitate taking funds away from other crucial transport initiatives in the region. The then-mayor of North Shore, Andrew Williams, and the then-chairman of the Auckland Regional Council, Mike Lee, both supported the earlier studies into a tunnel. The then-mayor of Auckland City, John Banks, also favoured the tunnel option, though he did not outright oppose the bridge idea, though the then-mayor of Manukau City, Len Brown, considered the bridge proposal worthy of consideration.
A more detailed concept for the bridge, published in late 2009, included eight traffic lanes (including separate truck and bus lanes) and two light rail tracks on a bridge deck alongside walking and cycling paths, possibly with travelators. Its designers claimed that the estimated NZ$2–3 billion cost of the bridge would be significantly cheaper than existing tunnel plans, estimated at NZ$4 billion.
In December 2009 NZTA announced that, though designations would be sought for new tunnel options, a future bridge was not being precluded so as to protect against conflict with future development in the Wynyard Quarter. The lobby group for the bridge regarded this as a success, though their original timeframe had been substantially pushed back with construction not planned to start until 2015. The centenary bridge planning group disbanded soon after, and there is now no organisation pursuing the bridge.
2010 study
In March 2010, tendering for another second crossing study was announced by Minister of Transport Steven Joyce. The decision was criticised in an editorial in The New Zealand Herald for wasting time and money, since the previous study only a few years earlier had already, at cost of over $1 million, conclusively ruled in favour of new tunnels over any new bridges.
The eventual report made a business case for three new harbour crossings—a bridge, a road tunnel, and a heavy rail tunnel—for a total estimated cost of $6 billion. The new bridge would have included tolled bike lanes.
2011 "Skypath"
To save waiting for an entirely new crossing, in 2011 NZTA proposed focusing on only part of the 2010 recommendations and adding new pedestrian and cycling paths onto the existing bridge. The plan initially had strong local support and was added to Auckland Transport's strategic priority list soon after, with resource consent sought and granted in 2016. The new Labour-led government elected in 2017 also pledged to fund the crossing.
However, concerns over the complexity of adding extra weight to the existing support columns led to the plan being revised in 2019, with Skypath instead proposed to run beneath the existing bridge on its own entirely independent set of columns. The plan was eventually cancelled altogether in 2021 after construction costs had grown to an estimated $785m, by which point planners argued that it would be more efficient to simply build an entirely new crossing altogether as originally planned. Local activists have continued to campaign for one of the existing bridge's lanes to be "liberated" for cycling, arguing that it would still provide a net increase to the bridge's capacity by encouraging commuters to switch away from cars. However, NZTA has repeatedly rejected requests for a trial lane after coming to the conclusion that collision risks to pedestrians and cyclists from passing traffic could not be mitigated.
2023 Waitematā Harbour Connections proposals
In 2019, NZTA commissioned consultancy firm PwC to examine the business cases for and against a wide range of second crossing options, taking into account historical proposals and current economic and demographic trends. The authors noted that 170,000 vehicles were crossing the bridge each day, including 11,000 trucks and more than 1,000 buses. While car passengers during peak hours (7-9am on weekdays) had remained largely static over the previous 25 years due to feeder roads on either side of the bridge having reached capacity, the total number of bus and truck journeys per day continued to grow, with 26,000 truck crossings predicted by 2046. The authors argued that previous road-plus-rail proposals would be less efficient than new heavy rail tunnels for cargo and passenger services.
-
Option 1
-
Option 2
-
Option 3
-
Option 4
-
Option 5
In March 2023 Transport Minister Michael Wood announced a public consultation on five options for new "Waitematā Harbour Connections", informed by the findings of the 2019 review. The options varied in scale and cost, with a mixture of tunnels, bridges, and different modes of transport, though all were intended to integrate with the planned Auckland Light Rail route between Auckland Airport and the CBD, with a station in the Wynyard Quarter:
- Option 1: Two new tunnels. A light rail line from Wynyard Quarter to Smales Farm via Belmont and Takapuna, and a road tunnel forming a new section of Highway 1 from Saint Mary's Bay to Akoranga Drive. The existing bridge would be reconfigured with more bus lanes and new pedestrian/cycle lanes. Total cost estimated at $25 billion (the most expensive of the options), with a 15-year construction timetable.
- Option 2: One new bridge, adjacent to the existing one with a mixture of car, bus, and pedestrian/cycle lanes, as well as a light rail line connecting the Wynyard Quarter to Takapuna via Akoranga Station. Total cost estimated at $15 billion, with a 10-year construction timetable. Noted in the government's announcement as the cheapest option, but also the least-resilient.
- Option 3: One new bridge, one new tunnel. A new light rail line running through the tunnel from the Wynyard Quarter to Takapuna via Birkenhead, Northcote, and Akoranga stations. The new bridge would combine car and pedestrian/cycle lanes to connect Westhaven to Northcote Point for vehicles travelling through Auckland, while local traffic would be concentrated on the existing bridge. 10-year construction timetable, but noted in the government's announcement as the least-efficient option in terms of increasing total cross-harbour capacity.
- Option 4: One new bridge, one new tunnel. A new bridge east of the existing one, connecting St Mary's Bay at its southern end to Sulphur Beach at the north, to carry pedestrian/cycle lanes as well as a new light rail line. The rail line would connect the Wynyard Quarter with Takapuna via Akoranga Station. The new road tunnel would form part of Highway 1 connecting Saint Mary's Bay to Akoranga Drive. 15-year construction timetable, and considered joint-most-efficient in terms of capacity by the government along with option five.
- Option 5: Identical to option four, except for the southern end of the new bridge would be located at the Wynyard Quarter instead of St Mary's Bay. 15-year construction timetable, and considered joint-most-efficient in terms of capacity by the government along with option four.
Work on the new crossing(s) was intended to begin in 2029. In August 2023, Transport Minister David Parker and Prime Minister Chris Hipkins announced that the consultation had led to a so-called "Emerging Preferred Option" which combined aspects from several of the earlier options:
- A tunnel for Auckland Light Rail, crossing from the Wynyard Quarter to Belmont on the North Shore before heading north via stations at Takapuna, Smales Farm Bus Station, Glenfield, North Harbour, Albany West and terminating at Albany Bus Station.
- Two new road tunnels (one for traffic in each direction) connecting the Central Motorway Junction directly to the North Shore, allowing national north–south through traffic to bypass the CBD entirely (with the existing Harbour Bridge reserved for local traffic).
- Upgrades to existing stations on the Northern Busway.
- "Significant upgrades" to the existing Harbour Bridge, and the raising of State Highway 1 from the bridge to Akoranga to protect it from sea level rise.
- Extending the Northern Busway across the existing bridge to the CBD from Akoranga by allocating it two dedicated lanes, and converting the eastern clip-ons into a fully separated active mode path, leaving the four remaining lanes for general traffic.
The overall cost was estimated as between $35 and $45 billion, which would make it the most expensive infrastructure project in New Zealand's history.
Immediate reactions from experts and commentators was mixed. Supporters of a new crossing in the Green party, Labour's coalition partners, were disappointed that the focus was on increasing road capacity rather than exclusively investing in public transit, whereas on the right Labour's political opponents (including Auckland Mayor Wayne Brown) pointed out that, with the 2023 General Election imminent, it appeared to be an unrealistic pre-election announcement which was overly expensive and unlikely to ever be delivered. National party leader Christopher Luxon expressed some support but with reservations over the proposed schedule and budget, describing it as "one of those projects we want to progress as well." National's transport spokesperson Simeon Brown—a longtime critic of Auckland Light Rail—criticised both the projected cost and the inclusion of a rail tunnel in the plans, but also expressed general support otherwise.
After National's subsequent win in the 2023 General Election the party announced Auckland Light Rail would be cancelled and its $14.6 billion budget spent on a number of road and highway upgrade schemes across New Zealand, including several new busways within Auckland. The proposed road tunnels under the harbour were also still being considered.
By December 2023, after having had time to review the plans in detail, all three of the Ministry of Transport, Auckland Transport, and Auckland City Council noted that there were "significant value-for-money issues" with them as currently proposed. Local planners also noted that without further funding from central government their only options for further transit investment in Auckland were new cycle lanes or continued upgrades to the Northern Busway. Waka Kotahi NZTA chief executive Nicole Rosie criticised the entire Waitematā Harbour Connections planning and consultation process, telling the New Zealand Herald that, "we're making the same decisions they would have made seven to ten years ago—all that's happened in the meantime is the population has grown, the issue has become more urgent, and the costs have gone up."
See also
- General
- Specific
- Central Motorway Junction, the major motorway junction connecting southeast of the bridge
- Newmarket Viaduct, similarly important traffic bottleneck on other side of Auckland CBD
- Western Reclamation, large industrial area east of the bridge, possible site of 2nd crossing
References
- ^ "Auckland's $4 billion second harbour crossing as far as 30 years away". North Shore Times/Stuff.co.nz. 2 November 2016. Retrieved 16 July 2017.
- ^ "Aucklanders' views sought on Waitematā Harbour Connections | Waka Kotahi NZ Transport Agency". nzta.govt.nz. Retrieved 8 June 2023.
- ^ "The history of the Auckland Harbour Bridge - Auckland News, Sport, Traffic and Weather from NZ Herald - NZ Herald News". 4 March 2016. Archived from the original on 4 March 2016. Retrieved 8 June 2023.
- ^ Dearnaley, Mathew (30 May 2009). "Agency in no hurry to replace bridge with harbour 'tubes'". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Phillips, Jock (11 March 2010). "The 'Nippon clip-ons'". Te Ara: The Encyclopedia of New Zealand. New Zealand Government. Archived from the original on 10 April 2023. Retrieved 17 June 2023.
- ^ "Editorial: Bridge at 50 uniting the city at last". The New Zealand Herald. 30 May 2009. Retrieved 7 November 2011.
- ^ Waitematā Harbour Crossing Study – Chapter 3, para. 3.1 – Project Objectives
- ^ Auckland City District Plan – Isthmus Section, Chapter 12.6.2.4 Second Harbour Crossing
- ^ "Auckland's Waterview Tunnel open to traffic at last". Stuff. 2 July 2017. Retrieved 2 July 2017.
- ^ Dearnaley, Mathew (11 July 2007). "Traffic decline casts shadow on $3b tunnel". The New Zealand Herald. Retrieved 7 November 2011.
- ^ "Auckland's Northern Busway to reach capacity a decade ahead of schedule". Stuff. 14 September 2017. Retrieved 29 November 2017.
- ^ "Plans for rail line through Auckland's North Shore to be determined this year". Stuff.co.nz. 14 March 2017. Retrieved 16 July 2017.
- ^ "The next harbour crossing: road and rail, or just rail". The New Zealand Herald. 9 March 2019. Retrieved 9 March 2019.
- ^ "Waka Kotahi Board confirms position on Auckland Harbour Bridge lane reallocation trial | Waka Kotahi NZ Transport Agency". www.nzta.govt.nz. Retrieved 24 June 2023.
- ^ Auckland, Greater (15 August 2022). "A Pathway to a Flourishing Future". Greater Auckland. Retrieved 24 June 2023.
- ^ Feasibility study – Watemata Harbour Second Crossing Archived 28 September 2007 at the Wayback Machine (from the Transit New Zealand website)
- ^ Welch, Timothy (3 April 2023). "A short history of doomed second harbour crossing proposals for Auckland – and a quicker, cheaper option". The Conversation. Retrieved 7 June 2023.
- ^ "Harbour Bridge future questioned". Television New Zealand. Radio New Zealand. 12 March 2006. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (10 July 2007). "Tank Farm route for $3b tunnel (+map)". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Gay, Edward (9 July 2007). "Bayswater tunnel could be part of harbour crossing study". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (3 December 2007). "New harbour crossing – it's down to Plan A or B". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (5 December 2007). "North Shore bosses want tunnel link". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Rudman, Brian (11 July 2007). "Brian Rudman: Hallelujah, talk before bulldozers". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Letters to the editor – Harbour tunnel – Wood, George; The New Zealand Herald, Saturday 14 July 2007, Page A22
- ^ Going underground – the latest option for Auckland commuters – LG – New Zealand Local Government, Volume 44 No 5, May 2008, Page 5
- ^ Key decisions on Auckland Harbour Bridge and third harbour crossing (NZ Transport Agency press release, Wednesday 2 December 2009. Retrieved 2009-12-02.)
- ^ Dearnaley, Mathew (1 June 2009). "Decision on harbour tunnels". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (12 July 2007). "Overhead option to Tank Farm tunnel". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (8 May 2007). "Photo: Longer, more elegant harbour bridge dreamed up". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Taylor, Phil (30 May 2009). "The art of bridging the gap". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Harward, Esther (18 October 2009). "Get foreign help to build next bridge". The Sunday Star-Times. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (4 December 2009). "City leaders urge minister to rule out new bridge". The New Zealand Herald. Retrieved 7 November 2011.
- ^ Horrell, Rhiannon (18 November 2009). "Bridge v tunnel for harbour". Central Leader. Retrieved 7 November 2011.
- ^ Dearnaley, Mathew (3 December 2009). "Minister raises hopes for new harbour link". The New Zealand Herald. Retrieved 7 November 2011.
- ^ "New Auckland Harbour Bridge, Harbour Bridge". 4 December 2009. Archived from the original on 4 December 2009. Retrieved 19 June 2023.
- ^ Rudman, Brian (19 March 2010). "No Minister, the tunnels have already won". The New Zealand Herald. Retrieved 26 March 2010.
- ^ https://www.nzta.govt.nz/assets/projects/awhc/docs/preliminary-business-case-report.pdf
- ^ Lowrie, Matt (22 March 2021). "Where to next for Skypath?". Greater Auckland. Retrieved 7 June 2023.
- ^ "Prime Minister Jacinda Ardern defends $51 million spent on cancelled Auckland cycle bridge". Newshub. Retrieved 7 June 2023.
- ^ "Govt scraps Auckland's $785m bridge cycleway". 1 News. Retrieved 7 June 2023.
- ^ Auckland, Bike (28 April 2021). "FAQ: Liberating The Lane". Bike Auckland. Retrieved 24 June 2023.
- ^ "New Zealand Offers Options for Next Auckland Harbor Crossing". Bloomberg.com. 29 March 2023. Retrieved 7 June 2023.
- ^ "Five options for new Auckland harbour crossing revealed". 1 News. Retrieved 7 June 2023.
- ^ Niall, Todd (29 March 2023). "Government unveils five options for second Auckland harbour crossing". Stuff. Retrieved 7 June 2023.
- ^ "About the project | Waka Kotahi NZ Transport Agency". nzta.govt.nz. Retrieved 8 June 2023.
- ^ Silva, Tommy de (31 March 2023). "The five Auckland harbour crossing proposals, explained". The Spinoff. Retrieved 7 June 2023.
- ^ Lowrie, Matt (29 March 2023). "Harbour Crossing Project now estimated to cost $15-25 billion". Greater Auckland. Retrieved 7 June 2023.
- ^ Agency, NZ Transport. "Waitematā Harbour Connections | Waka Kotahi NZ Transport Agency". www.nzta.govt.nz. Retrieved 16 October 2023.
- ^ "Phased tunnels for second Harbour crossing". The Beehive. Retrieved 16 October 2023.
- ^ Menteth, Thames (11 August 2023). "Three new tunnels planned for Auckland harbour to cost up to £21.4bn". Ground Engineering (GE). Retrieved 16 October 2023.
- ^ "'No question' second Auckland harbour crossing needed - PM". The New Zealand Herald. 17 October 2023. Retrieved 16 October 2023.
- ^ "Labour's 'complex beast' of a transport plan divides Auckland". Newsroom. 8 August 2023. Retrieved 16 October 2023.
- ^ Lewis, Oliver. "Auckland harbour crossing just 'electioneering'". businessdesk.co.nz. Retrieved 16 October 2023.
- ^ "'Bonkers': Greens slam second harbour crossing as National shows support". The New Zealand Herald. 17 October 2023. Retrieved 16 October 2023.
- ^ "National to derail Auckland's light rail". Newsroom. 13 July 2023. Retrieved 16 October 2023.
- ^ "Mixed reaction to government's multi-billion Auckland harbour tunnels plan". RNZ. 7 August 2023. Retrieved 16 October 2023.
- ^ "National to scrap $14.6b light rail project". The New Zealand Herald. 18 January 2024. Retrieved 18 January 2024.
- ^ "Auckland's new $56b harbour crossing heading for the rocks". The New Zealand Herald. 18 January 2024. Retrieved 18 January 2024.