Snoqualmie Falls Hydroelectric Plant
Plant 1 was added to the National Register of Historic Places as Snoqualmie Falls Cavity Generating Station on April 23, 1976. In 1981, Plant 1 was also designated as an National Historic Civil Engineering Landmark by the American Society of Civil Engineers. The power plant is owned by Puget Sound Energy. In 1992, Snoqualmie Falls Hydroelectric Power Plant Historic District was added to the National Register of Historic Places.
History
The power plant was envisioned by Charles H. Baker in the 1890s. Baker was an engineer for the Seattle, Lake Shore and Eastern Railway and would pass the Snoqualmie Falls routinely during his work. Similar to the Schoellkopf Power Station on Niagara Falls in New York, Baker wanted to exploit the drop in elevation of Snoqualmie Falls for hydroelectric power. After the Panic of 1893 he became unemployed and sought to build the power plant. With funding from his family, to include his father, wealthy businessman William T. Baker, he formed the Snoqualmie Falls Power Company and bought the falls and surrounding land in 1897. Construction on the plant began in 1898. First, a cofferdam was constructed to seal the river from the water intake on the left bank of the Snoqualmie Falls. Steam-powered pneumatic drills were then used to excavate a vertical shaft from the intake to the cavern for Plant 1. A horizontal tunnel was dug as well, which met the vertical shaft at the cavern for Plant 1. A weir was constructed downstream of the intake and just above the falls, to help raise the river above the intake so water could be delivered to the plant. Four Pelton turbines with 1.5 MW Westinghouse generators were initially installed. The first operational generator was online and began to transmit power to Seattle on July 31, 1899. The remainder were commissioned and delivering power to Tacoma as well on November 1, 1899. In 1903 Seattle Electric Company acquired Snoqualmie Falls Power Company. The death of William Baker and financial difficulties that same year ended Charles Baker's stake in the plant. A fifth turbine-generator, horizontal Francis-type, originally rated at 5 MW, was added to Plant 1 in 1905. In 1908 Seattle-Tacoma Power Company, a forerunner to Puget Sound Energy, purchased Seattle Electric Company.
The penstock was supplied and installed by Chicago Bridge & Iron Co.
Soon after the fifth generator was added to Plant 1, plans for Plant 2 began. Engineer W.A. Brackenridge studied and designed the plant. It would include a tunnel from the weir connected to a forebay would supply water to the future Plant 2, located just downstream from the falls. Plant 2 was commissioned in 1910 with a single 9 MW Francis turbine-generator. To make future expansion possible, the tunnel and penstock were built large enough to supply up to three generators. Plant 2 underwent an expansion beginning in 1956. A second Francis turbine-generator was installed and commissioned in 1957. A larger second penstock was also installed as the new generator was much larger than earlier planned. At this time, the entire power plant had an installed capacity of 44.4 MW. The second turbine for Plant 2 was replaced in 1991 due to end-of-life and it was once again replaced in 2004 as it was damaged by sediment. In 2004, Puget Sound Energy was granted a new 40 year license from the Federal Energy Regulatory Commission which required that the plant maintain a consistent discharge equal to or greater than 30 cu ft/s (0.85 m/s).
Rehabilitation and upgrade
In April 2010, Puget Sound Energy began a US$200 million project to rehabilitate and upgrade the power plant. The project included retrofitting the first four of the generators in Plant 1 and replacing the fifth. A turbine-generator would be replaced in Plant 2 as well. The weir was lowered to 16 ft (4.9 m) in height, lengthened by 37 ft (11 m) and the water-intake structure was replaced. Lowering the weir will help reduce flood waters upstream of the falls. The penstocks, which feed the power plants with water, were to be upgraded as well. Finally, automatic shut-off and bypass valves were installed for Plant 2. The shut-off valves will better prepare the plant for emergencies and the bypass valves will allow water to flow downstream in the case that Plant 2 is offline. To promote tourism, recreation and culture, several upgrades to include new visitor centers, hiking trails, a boardwalk and improved landscaping were implemented. Renovations on Plant 2 were completed in April 2013. The new 6.5 MW Francis turbine generator in Plant 1 and the entire project was finished in mid-2014. The project raised the installed capacity of the power plant from 44.4 MW to 53.9 MW.
Design
To supply water to Plant 1 and 2, a weir with a height ranging 4–16 ft (1.2–4.9 m) creates a small reservoir. The intake for Plant 1 is located just above the left abutment of the weir. Water from the intake enters a 280 ft (85 m) long and 7 ft (2.1 m) diameter vertical penstock which supplies water to the plant. Plant 1 is located in a cavern 270 ft (82 m) below and about 300 ft (91 m) behind the falls. The cavern is 200 ft (61 m) long, 40 ft (12 m) wide and 30 ft (9.1 m) high. It houses four 1.8 MW Pelton turbine-generators and one 6.5 MW Francis turbine-generator. Water discharged from Plant 1, at a rate of up to 700 cu ft/s (20 m/s), is returned to the river below the falls via a 650 ft (200 m) long tailrace tunnel.
The intake for Plant 2 is located near the right abutment of the weir. Water first enters a tunnel along a ridge which parallels the river downstream of the falls. It reaches a forebay which temporarily stores water before it is sent to the plant. From the forebay, a gatehouse releases water into two penstocks, each roughly 520 ft (160 m) with the larger having a diameter of 10 ft (3.0 m). The penstocks connect to Plant 2 which is located on the right bank of the Snoqualmie River. It houses a 13.7 MW and a 26.5 MW Francis turbine-generator. Water discharged from Plant 2, at a rate of up 1,800 cu ft/s (51 m/s), immediately enters the river.
References
- ^ "Snoqualmie Falls Hydroelectric Project". Snoqualmie Falls. March 11, 2010. Retrieved January 23, 2015.
- ^ "Snoqualmie Falls Hydroelectric Project". Puget Sound Energy. Retrieved January 23, 2015.
- ^ "Snoqualmie Falls Cavity Generating Station". American Society of Civil Engineers. Retrieved February 6, 2022.
- ^ Wiegand, Paul (April 23, 2014). "Renovation Marries History, Technology and Environment". HydroWorld. Retrieved January 23, 2015.
- ^ "Snoqualmie Falls Cavity Generating Station". National Register of Historic Places. Retrieved January 23, 2015.
- ^ Killgore, Mark W.; Dubreil, Elizabeth; Rogers, Jerry R. (2011). "Snoqualmie Falls Hydropower Plant—A National Historic Civil Engineering Landmark". World Environmental and Water Resources Congress. doi:10.1061/41173(414)197.
- ^ Theodore Catton, Gail Thompson (November 1991). "National Register of Historic Places Inventory/Nomination: Snoqualmie Falls Hydroelectric Power Plant Historic District". National Park Service. Retrieved May 19, 2019. With 10 accompanying pictures
- ^ "Snoqualmie Falls: One man's vision". Water Power and Dam Construction. January 4, 2012. Retrieved January 23, 2015.
- ^ "Baker, Charles H. (Charles Hinckley)". University of Virginia - Institute for Advanced Technology in the Humanities. Retrieved January 23, 2015.
- ^ "Guide to the Snoqualmie Falls in Harness: Souvenir of the Visit of the Commercial Club of Chicago Photograph Album". University of Washington Libraries Special Collections. Retrieved January 23, 2015.
- ^ "Snoqualmie Falls Plant No. 2: Restoring a Renewable Resource". HydroWorld. November 1, 2010. Retrieved January 23, 2015.
- ^ "NRHP Nomination Form - Snoqualmie Falls Cavity Generating Station". National Record of Historic Places. March 17, 1976. Retrieved January 23, 2015.
- ^ "About the Snoqualmie Falls Project". Puget Sound Energy. Retrieved January 24, 2015.
- ^ "Snoqualmie Falls Hydropower Redevelopment". Kleinfelder. Retrieved January 23, 2015.
- ^ "PSE to Make Major Enhancements at Snoqualmie Falls Hydro Project". Bloomberg News. Business Wire. June 4, 2009. Retrieved January 23, 2015.
- ^ "Snoqualmie Falls Redevelopment Project" (PDF). Puget Sound Energy. Retrieved January 23, 2015.
- ^ "Snoqualmie Falls Redevelopment Project; Conforming to New License Requirements; and Maximizing Efficiency" (PDF). Puget Sound Energy. May 21, 2014. Retrieved January 24, 2015.
External links
- Snoqualmie Falls Hydroelectric Project at Puget Sound Energy
- Snoqualmie Falls Hydroelectric Project at SnoqualmieFalls.com
- Snoqualmie Falls Cavity Generating Station at the ASCE
- 1902 Scientific American
- HAER No. WA-21, "Snoqualmie Falls Hydroelectric Project", 24 photos, 12 data pages, 2 photo caption pages
- HAER No. WA-21-A, "Snoqualmie Falls Hydroelectric Project, Dam", 5 data pages
- HAER No. WA-21-B, "Snoqualmie Falls Hydroelectric Project, Plant One Intake, Penstocks, Underground Cavity, and Tailrace", 15 data pages
- HAER No. WA-21-C, "Snoqualmie Falls Hydroelectric Project, Elevator House", 1 photo, 4 data pages, 1 photo caption page
- HAER No. WA-21-D, "Snoqualmie Falls Hydroelectric Project, Transformer House", 7 photos, 6 data pages, 1 photo caption page
- HAER No. WA-21-E, "Snoqualmie Falls Hydroelectric Project, Machine Shop", 5 photos, 5 data pages, 1 photo caption page
- HAER No. WA-21-F, "Snoqualmie Falls Hydroelectric Project, Carpenter Shop", 2 photos, 3 data pages, 1 photo caption page
- HAER No. WA-21-G, "Snoqualmie Falls Hydroelectric Project, Train Depot", 2 data pages
- HAER No. WA-21-H, "Snoqualmie Falls Hydroelectric Project, West Garage", 2 data pages
- HAER No. WA-21-I, "Snoqualmie Falls Hydroelectric Project, Cottage No. 4", 2 photos, 2 data pages, 1 photo caption page
- HAER No. WA-21-J, "Snoqualmie Falls Hydroelectric Project, Cottage No. 1", 2 photos, 2 data pages, 1 photo caption page
- HAER No. WA-21-K, "Snoqualmie Falls Hydroelectric Project, Plant Two Powerhouse", 5 photos, 8 data pages, 1 photo caption page
- HAER No. WA-21-L, "Snoqualmie Falls Hydroelectric Project, Intake Two, Tunnel Portals, Forebay, Gatehouse, and Penstocks", 6 photos, 10 data pages, 1 photo caption page
- HAER No. WA-21-M, "Snoqualmie Falls Hydroelectric Project, Shed", 2 data pages