Twin Sails Bridge
Location
The bridge spans the Backwater Channel which links Holes Bay with Poole Harbour. The bridge and approach roads are connected to the junction of West Quay Road in the East and to urban feeder roads in the West.
Design
The new bridge is intended to operate alongside the existing Poole Bridge with one of the bridges always open for vehicular traffic (except during closures for maintenance or in a marine emergency), the intention is that variable-message signs will direct traffic to the open bridge. The bridge comprises a 10.8-metre (35 ft) wide carriageway with two vehicular lanes and two separate cycle lanes. Additionally two 2.5-metre (8 ft) wide footpaths are provided which cantilever from the bridge. The bridge is constructed in five spans, with a total length of roughly 139 metres (456 ft). The approaches comprise two 27-metre (89 ft) spans, the centre lifting span consists of two triangular leaves that span 23.4 metres (77 ft) between the main bearings to provide a clear channel of 19 metres (62 ft) when open. To permit the passage of boats through the navigation channel, the lift spans were planned to pivot to 88 degrees powered by two hydraulic rams which operate up to 15 times per day and take two minutes to fully open. Two 55-metre (180 ft) high masts are fitted to the lifting leaves, the top two metres illuminated with white LED lights. Four 7-metre (23 ft) high pillars housing the barriers, lights, speakers and traffic controls which link the bridge with the control room are located on the two fixed spans adjacent to the lifting section.
Hochtief (UK) Construction was awarded the £18.5 million contract for the construction of the bridge. The contract for the supply of around 900 tonnes of steel was awarded to Cleveland Bridge UK. Gifford UK (Ramboll) worked with Wilkinson Eyre Architects as lead design consultants. Metamont Ltd installed marine grade stainless steel balustrade including the variable colour DMX lighting.
History
Plans for a new bridge date to the 1980s, with the second lifting bridge concept being suggested in 2000 after a fixed bridge crossing Holes Bay and linking with the A31 was cancelled by the government in 1998. The council submitted detailed plans to Department for Transport in 2004 and following a public inquiry in 2005, the £37 million Twin Sails bridge project was given approval in 2006/7 but construction was initially delayed due to a stalemate between the council and the land owners. After negotiations were settled in August 2009, there was a further delay in the allocation of the £14.14 million government grant which was finally agreed in March 2010.
Construction began in May 2010 with completion and opening planned for late February 2012. Problems with the road surface caused the bridge to remain closed although the opening ceremony and visit by The Princess Royal went ahead in early March 2012. The bridge opened to traffic on 4 April 2012 after the road surface had been relaid, the first motor vehicle crossing at 9.38AM. Problems with the bridge operation continued in the summer of 2012 with delays caused through the barrier operation and lifting mechanism as well as continuing defects in the road surface.
The bridge was closed again beginning 16 November 2018 due to a hydraulic issue with its lifting mechanism.
In 2019 BCP Council, which Poole Borough Council was absorbed by, convened an emergency meeting due to the issues with the bridge becoming "unacceptable".
The bridge continued to be closed down due to technical problems up to 2020. These design issues are apparently caused by a design issue with the bridge as the bridge itself has an unusual design compared to a typical bascule bridge.
On 16 January 2023, a section of the bridge snapped due to a technical fault.
Since early July of 2024, the bridge has been closed due to a major technical fault. The bridge was only meant to be closed for two weeks, however, large technical issues have been found in the bridge, causing it to get stuck regularly. Engineers are looking into this and are working on the bridge becoming operational once again. However, there is no date for the to be completed, meaning that the bridge will remain in an opened position for all ships to access.
References
- ^ Serck, Linda (4 February 2011). "Twin Sails Bridge divides opinion in Poole". BBC News. Retrieved 6 February 2012.
- ^ "Twin Sails Bridge – On Time And on Budget | Poole". Pooleconservatives.org. 6 December 2012. Retrieved 8 February 2012.
- ^ "Twin Sails Bridge". Ramboll. Retrieved 16 December 2012.
- ^ "Twin Sails Bridge". Road Traffic Technology. 15 June 2011. Retrieved 8 February 2012.
- ^ "Twin Sails – Poole's bridge for the future" (PDF). Borough of Poole. Retrieved 8 February 2012.
- ^ "Twin Sails Bridge rises to the challenge". Daily Echo. 15 October 2011. Retrieved 8 February 2012.
- ^ "Poole's Twin Sails Bridge set for opening". Daily Echo. 3 February 2012. Retrieved 12 February 2012.
- ^ "Twin Sails Bridge". Road Traffic Technology. 15 June 2011. Retrieved 5 February 2012.
- ^ "Inquiry into town bridge". BBC News. 27 September 2005. Retrieved 5 February 2012.
- ^ "Twin bridge is given the go-ahead". BBC News. 11 August 2006. Retrieved 5 February 2012.
- ^ "Twin Sails – 30-year history" (PDF). Borough of Poole. 27 January 2011. Retrieved 12 February 2012.
- ^ "Go ahead for Poole's Twin Sails Bridge". Daily Echo. 13 March 2010. Retrieved 5 February 2012.
- ^ Henderson, Diana (21 March 2012). "Twin Sails bridge: no solution yet as asphalt removed from road surface". Bournemouth Echo. Retrieved 21 March 2012.
- ^ Henderson, Diana (4 April 2012). "At last: Poole's Twin Sails bridge is to open to traffic". Bournemouth Echo. Retrieved 4 April 2012.
- ^ Codd, Joanna (12 July 2012). "Council demands contractors fix Twin Sails Bridge after series of shutdowns". Bournemouth Echo. Retrieved 27 July 2012.
- ^ "Construction firm WILL pay council for Poole Bridge problems". Bournemouth Echo. Retrieved 28 November 2018.
- ^ "Report on Twin Sails bridge fault expected early next week, Poole councillor says". Bournemouth Echo. Retrieved 28 November 2018.
- ^ "'We don't know what's wrong or when the Twin Sails bridge will reopen'". Bournemouth Echo. Retrieved 28 November 2018.
- ^ "Anger at 'lack of information' as major route in Poole remains closed". ITV News. Retrieved 28 November 2018.
- ^ "Emergency summit called after the Twin Sails Bridge breaks down... again". Bournemouth Echo. Retrieved 28 March 2021.
- ^ "Poole's Twin Sails Bridge repairs halted after problems". BBC News. 11 December 2020. Retrieved 28 March 2021.
- ^ "Twin Sails Bridge 'isn't a maintenance problem, it is a design issue'". Bournemouth Echo. Retrieved 28 March 2021.
- ^ "Part of Twin Sails Bridge snapped during lift - with no word on when it will be fixed". Bournemouth Echo. Retrieved 17 January 2023.
- ^ "No end in sight to finish disastrous Twin Sails Bridge work, council confirms". Bournemouth Echo. 16 July 2024. Retrieved 27 July 2024.