Wanjiazhai Dam
Construction
The State Planning Commission approved construction of the dam in 1993. At the end of 1994, construction on the dam began and by December 1995, the river was diverted around the construction site. On October 1, 1998, the dam began to impound the reservoir and the first generator went online on November 28, 1998. Two more generators went online in 1999 and the final three in 2000.
Dam design
The dam is a 105 m (344 ft) tall and 443 m (1,453 ft) long concrete gravity dam that withholds a reservoir with 896,000,000 m (726,399 acre⋅ft) of water, 445,000,000 m (360,767 acre⋅ft) of which is the regulating capacity. The dam's power plant contains 6 x 180 MW Francis Turbine-generators for an installed capacity of 1,080 MW.
Wanjiazhai Water Control Project
Also known as the Wanjiazhai Water Transfer Project or Shanxi Wanjiazhai Yellow River Diversion Project, it is designed to alleviate water shortages in Taiyuan, Shuozhou and Datong and provide electricity for areas around the dam. First, water derived from the Wanjiazhai Dam's reservoir is pumped through the 44 km (27 mi) long General Main at a rate up to 48 m/s (1,695 cu ft/s), being assisted by three pump stations and the Shentongzui Reservoir along the way. At Xiatuzhai village, the General Main reaches a diversion sluice where it splits into the South Main and the North Main. Traveling at a rate of 20.5 m/s (724 cu ft/s), water moves through the South Main for a distance of 102 km (63 mi) to Fenhe River and then the Fenhe Reservoir 38°04′01″N 111°53′48″E / 38.06694°N 111.89667°E near Taiyuan. The South Main is intended to deliver 640,000,000 m (518,856 acre⋅ft) of water a year. The North Main, beginning at Xiatuzhai, travels northward for a distance of 167 km (104 mi) at a rate of 22.2 m/s (784 cu ft/s), being assisted during its route by the Daliang Reservoir and pump station. The North Main terminates at the Zhaojiaxiaocun Reservoir near Datong.
Contracts for the water control project were awarded in 2001 and by the end of the year, the first step was complete when Yellow River water flowed into the Fehne Reservoir. The entire cost of the project is $1.5 billion, $500 million is being funded by the World Bank.
See also
References
- ^ "Hydroelectric Power Plants in China - other provinces". IndustCards. Archived from the original on September 7, 2012. Retrieved 12 January 2011.
{{cite web}}
: CS1 maint: unfit URL (link) - ^ "Wanjiazhai Water Control Project". China Internet Information Center. Retrieved 12 January 2011.
- ^ Proceedings of the 30th International Geological Congress : Beijing, China, 4-14 August, 1996. Utrecht: VSP. 1997. p. 159. ISBN 90-6764-276-2.
- ^ "Wanjiazhai Yellow River Diversion Project" (PDF). Liquis. pp. 1–3. Archived from the original (PDF) on 23 July 2011. Retrieved 12 January 2011.
- ^ "Shanxi Wanjiazhai Yellow River Diversion Project, China". Water-Technology. Retrieved 12 January 2011.