West Springfield Generating Station
The plant was shut down in June 2022 and is scheduled to be demolished. The generators have been sold and dismantling had begun in the summer of 2022 with the jet turbine disconnected and removed from the site by August 2022.
Information
The station is located south of the Memorial Bridge in West Springfield, Massachusetts. The power plant and the adjacent West Springfield Substation were built in 1949 by Western Massachusetts Electric Company, a subsidiary of Northeast Utilities (now Eversource Energy). The original station consisted of two simple-cycle steam units (Units 1 and 2) which burned both oil and coal at different periods of their existence. Unit 3 was added in 1957 and the jet turbine was added in 1969. In 1999 the Station was acquired by Con Edison and the plant's corporate name became Con Edison Energy Massachusetts, Inc. By that time, the plant had become a reserve facility only used at times of very high system load. In 2002, Con Edison converted the plant into a peaking facility by replacing the original boiler Units 1 and 2 with the current combustion turbines. The facility did not operate often and was primarily used to maintain grid reliability in the area. Due to the current New England market conditions, none of the plant's units fared well, revenue-wise, but in 2005 it was determined by ISO New England that the station was needed for reliability purposes and CEEMI was awarded Reliability Must Run agreements in 2005 from ISO New England for the station's units. In RMR agreements, the electricity market agrees to subsidize the costs of operating units which are deemed necessary but are unable to make enough revenue to pay operational costs. Generally these are paid for by increasing electricity rates to customers. In 2008, Con Edison sold CEEMI to North American Energy Alliance, Inc. now known as Essential Power LLC, which is a joint venture owned by AllCapital and IFM. Essential Power was subsequently acquired by Cogentrix Energy, under ownership of funds managed by The Carlyle Group. In 2019, the plant did not receive a contract to supply peak power and the owners decided to decommission it.
Steam Units 1 and 2 are permanently retired as of December 31, 2000 (last used in 1999) and the boilers are currently being decommissioned. During the decommissioning of Units 1 and 2 and installation of CTG-1 and CTG-2, the plant's coal chute located on the outside of the boiler hall was removed and the original brick exhaust stacks were replaced with metallic stacks. The two simple-cycle, gas-fired combustion turbine generators (CTGs) having a total nominal capacity of 98 MW were installed and began operating June 5, 2002. Gas turbines are capable of starting up and responding much faster to changing electricity demand than steam units, thus the CTGs are much more desirable as peaking units than the original boilers. In addition, the CTGs emit far less air pollution and require far less cooling water. Each exhaust housing contains selective catalytic reduction (SCR) and an oxidation catalyst system for the control of nitrogen oxides (NOx). The company did not install a heat recovery steam generator with these units.
The plant used the Connecticut River as its source of cooling water. Unit 3, as a steam unit, had to reject waste heat from its condenser to a water source. A once-through cooling system utilizing water from the river removed waste heat from Unit 3's condenser. The circulating water pumps are located in the plant's pump house across the highway from the facility directly on the Connecticut River. Unit 3 could require up to 6 million gallons per day of water when operating. Units 1, 2, and 10 rejected all of their waste heat from combustion to the atmosphere via the exhaust stacks. However, Units 1 and 2 required a small amount of cooling water to remove heat from the lubricating oil system for the turbines. A small service water system operating at 730 gpm continuously provided cooling water for that purpose. Unit 10 did not require any cooling water at all.
Units 1 and 2 had an operational constraint of 4800 hours/year based on the Massachusetts Department of Environmental Protection (MA DEP) Air Quality Plan Approval. The MA DEP has recently granted approval to NAEA to operate the units an additional 720 hours per year using distillate fuel oil. According to the plant management, Unit 3 could operate at about 10–20% of its capacity.
Electricity was supplied to the grid at the adjacent Eversource Energy owned substation located directly behind the plant. All four units generated power at 13.8 kilovolts (kV). Units 1 and 10 supplied power directly via the 13.8 kV local distribution system fed out of the substation. Unit 3, and since 2002 unit 2, supplied power to the 115 kV transmission switchyard at the substation via generator step-up transformers (GSU). The plant could be started with no off-site power available and with only the on-site emergency diesel generator providing electricity to plant systems. As a result, the West Springfield plant was capable of starting and supplying power to local loads in the event of a complete grid failure or in the event that the utility substation through which it transmits power is isolated from the rest of the grid, known as "black start" capability.
Owned by Cogentrix Energy, the West Springfield Generating Station is located at 15 Agawam Ave. in West Springfield, Massachusetts.
Installed equipment
Unit No. | Description | Capacity | Start date | Fuel |
---|---|---|---|---|
1 | Combustion Engineering Boiler | 48 MW | Decommissioned | No. 6 Fuel oil |
2 | Combustion Engineering Boiler | 48 MW | Decommissioned | No. 6 Fuel oil |
CT-1 | Combustion turbine | 49 MW | 2002 | N. gas / ultra low-sulfur diesel (ULSD) |
CT-2 | Combustion turbine | 49 MW | 2002 | N. gas / ultra low-sulfur diesel (ULSD) |
3 | Combustion Engineering Boiler | 107 MW | 1957 | No. 6 Fuel Oil / N. gas / ultra low-sulfur diesel (ULSD) |
10 | Pratt & Whitney FT4a-8LF Combustion turbine | 18 MW | 1969 | ultra low-sulfur kerosene (ULSK) |
Doreen Street | Pratt & Whitney FT4a-8LF Combustion turbine | 18 MW | ultra low-sulfur kerosene (ULSK) | |
Woodland Road | Pratt & Whitney FT4a-8LF combustion turbine | 18 MW | ultra low-sulfur kerosene (ULSK) | |
Aux. Boiler | Cleaver Brooks Package boiler | 14MM BTU/hr (heat only) | 1994 | No. 2 Fuel oil |
Emergency Generator | Reiner Generator set | 5 KW | 1955 | Natural gas |
References
- ^ Munford, Aprell May (2023-04-24). "West Springfield explores redevelopment of old power plant". masslive.com. The Springfield Republican. Retrieved 2023-06-17.
- ^ Dobbs, G. Michael (2022-12-07). "State funds will help determine future of closed power plant". thereminder.com. The Reminder. Retrieved 2023-06-17.
- ^ EPA response to NPDES Permit No. MA0004707