Woodlands North MRT Station
The station was one of the first three TEL stations to be opened on 31 January 2020 as part of Stage 1. During its construction, plans were made for the station to be linked with the Johor Bahru–Singapore RTS, which was confirmed in 2012. Construction began in 2021, and it will be the Singapore terminus of the RTS when it is completed by 2026.
History
The station was first announced as part of the 22-station Thomson Line (TSL) on 29 August 2012. Contract T202 for the design and construction of Woodlands North Station and associated tunnels was awarded to Penta-Ocean Construction Co Ltd for S$337 million (US$247 million) in November 2013. Construction started in 2014 with a scheduled completion date of 2019.
On 15 August 2014, the Land Transport Authority (LTA) announced that TSL would merge with the Eastern Region Line to form the Thomson–East Coast Line (TEL). The station was constructed as part of Phase 1 (TEL1), consisting of three stations between this station and Woodlands South.
On 19 September 2019, it was announced by then Transport Minister Khaw Boon Wan that TEL1 will open before the end of January 2020. The LTA later announced in December that the TEL1 stations would be opened on 31 January 2020. Before the stations commenced operations on that day, an open house for the TEL 1 stations was held on 11 January 2020.
RTS Link
In June 2011, it was announced that the northern terminus of the TEL will be connected to the proposed cross border rail link. On 16 January 2018, a bilateral agreement on the project was signed between Malaysia and Singapore, during the 8th Singapore-Malaysia Leaders' Retreat. The agreement finalised certain aspects of the project, including its maintenance facilities, operator, and customs facilities.
However, the project was postponed on 21 May 2019 due to financial implications on Malaysia's side. On 31 October that year, Malaysia agreed to resume the RTS project at a lower cost although the project is still suspended until 30 April 2020. Due to the COVID-19 pandemic, it was agreed that the project be suspended further until 31 July 2020. The project officially resumed on 30 July 2020 with a new completion target by end 2026.
The contract for the construction of the RTS Link Woodlands North station and associated tunnels was awarded to Penta-Ocean Construction Co Ltd for S$932.8 million (US$683.8 million). The contract includes the construction of Singapore's Customs, Immigration, and Quarantine (CIQ) building. Construction is expected to begin in the first quarter of 2021, with expected completion by the end of 2026. On 22 January 2021, construction of the Singaporean side of the RTS link began with a groundbreaking ceremony near the station. On 29 January 2021, China Communications Construction Company Limited (Singapore branch) was awarded the second contract to construct tunnels and viaducts at a value of S$180 million (US$135.24 million). The King of Malaysia Ibrahim Iskandar of Johor visited the station on 7 May 2024 during his state visit to Singapore.