Preparations for the Yamal's development started in the 1990s. According to the original plans, drilling work on the Bovanenkovo field was to have started in 1997. In January 2002, Gazprom identified the Yamal Peninsula as a region of Gazprom's strategic interest. Preparatory works started in 2007 with the construction of auxiliary infrastructures, such as staff buildings and transport facilities. In July 2008 Gazprom launched the construction of the Bovanenkovo–Ukhta gas trunkline at the submerged crossing via the Baydaratskaya Bay. The project was officially inaugurated on 3 December 2008.
As of 2020, Yamal produces about 20% of Russia's natural gas, which is expected to increase to 40% by 2030.
Oil and gas fields
As of 2008, Gazprom listed 11 gas fields and 15 oil, gas and condensate fields on the Yamal Peninsula and the Yamal shelf in the Kara Sea. They consisted of 16 trillion cubic meters (tcm) of explored and provisionally evaluated gas reserves, and nearly 22 tcm of in-place and forecast gas reserves. Estimated condensate reserves were 230.7 million tonnes; estimated oil reserves were 291.8 million tonnes. The largest gas fields for which Gazprom owns the licenses were the Bovanenkovo, Kharasavey, Novoportovo, Kruzenshtern, Severo-Tambey, Zapadno-Tambey, Tasiy and Malygin fields.
As of 2021, Gazprom listed 18 fields it has licenses for in the Yamal Peninsula and offshore, only a few of which were in production. Evaluated reserves for these fields were given as 20.4 trillion cubic meters (tcm) of gas and 1 billion tonnes of gas condensate and oil. In 2020 99.25 billion cubic meters (bcm) of gas was produced.
Bovanenkovo gas field
The Bovanenkovo gas field is the largest gas field on the Yamal Peninsula with estimated reserves of 4.9 tcm. In 2020 production was 99 billion cubic metres (3.5×10 cu ft), of its nominal production capacity of 115 billion cubic metres (4.1×10 cu ft) per year.
Yamal LNG
In November 2008, Gazprom announced that it had a list of potential partners for the Yamal LNG project. Ultimately however Novatek was the principal shareholder, and commercial operation started in December 2017 with the loading of the first LNG carrier.
Transport
The 572 kilometres (355 mi) Obskaya–Bovanenkovo railway was opened in 2011 to provide all year access to the Bovanenkovo gas field. The port at Kharasavey gas field can be used in the summer. The gas fields are also served by the Bovanenkovo Airport (IATA: BVJ).
The Arctic Gate offshore oil loading terminal is located in the Gulf of Ob, designed to operate where ice could be over two meters thick.
Trunk pipelines
A joint project (Yamal-Europe pipeline) between gas transportation companies of Russia, Belarus, Poland and Germany was agreed in 1993 and commissioned in 1999. After commissioning of the Bovanenkovo–Ukhta gas trunkline it will deliver Yamal's gas to Europe. Construction of this pipeline started in July 2008 and was officially launched on 3 December 2008. The 1,100 kilometres (680 mi) gas pipeline is to connect the Bovanenkovo gas field with the Russian gas hub at Ukhta. First deliveries of over 15 bcm per year were originally expected to start by the end of 2011, but actual pipeline filling with natural gas started on 15 June 2012.
The shortest pipeline routes from Yamal to the northern EU countries are the Yamal–Europe pipeline through Poland and Nord Stream 1 to Germany. The proposed gas route from Western Siberia to China is known as Power of Siberia 2 pipeline.
See also
References
- ^ "Gazprom starts developing the Yamal gas fields". East Week (150). The Centre for Eastern Studies. 17 December 2008. Retrieved 1 January 2009.
- ^ "Gazprom launches Yamal megaproject" (Press release). Gazprom. 1 January 2009. Archived from the original on 18 December 2008. Retrieved 1 January 2009.
- ^ Yermakov, Vitaly (September 2021). Big Bounce: Russian gas amid market tightness (PDF) (Report). Oxford Institute for Energy Studies. Fig 16.
- ^ "Yamal". Gazprom. Archived from the original on 23 December 2021. Retrieved 8 November 2021.
- ^ Yermakov, Vitaly (September 2021). Big Bounce: Russian gas amid market tightness (PDF) (Report). Oxford Institute for Energy Studies. p. 21. Retrieved 1 November 2021.
- ^ "Gazprom makes Yamal LNG partner list". Upstream Online. NHST Media Group. 18 November 2008. Retrieved 1 January 2009.
- ^ Foy, Henry (8 December 2017). "Russia ships first gas from $27bn Arctic project". Financial Times. Retrieved 10 June 2018.
- ^ "Obskaya – Bovanenkovo railroad". Gazprom. Retrieved 4 November 2021.
- ^ Staalesen, Atle (16 December 2020). "Ships flock in icy Ob Bay as new grand seaport rises". The Barents Observer. Retrieved 8 November 2021.
- ^ First Gas Feeds to Bovanenkovo-Ukhta GTS, Natural Gas Europe, retrieved 20 June 2012
- ^ "'Power of Siberia 2' Pipeline Could See Europe, China Compete for Russian Gas". VOA News. 18 January 2022.
External links
- Yamal Megaproject Archived 18 August 2020 at the Wayback Machine (Gazprom website)