Narayanpur Dam
Gates
There are thirty spillway gates built into the dam. Each of these spillway gates are of the Ogee type. It is a common and basic design which transfers excess water from behind the dam down a smooth incline into the river below. These are usually designed following an ogee curve. Most often, they are lined on the bottom and sides with concrete to protect the dam and topography. The dam falls under the Parliamentary Constituency of Vijayapura, and it is classified as being an earthen/ gravity and masonry build type.
When it was completed in 1982 it provided water to irrigate 4.21 lakh hectares in Jewargi taluka in Kalaburagi district, Shahapur and Shorapur talukas in Yadgir district, Sindagi and Indi talukas in Bijapur district, and Lingsugur and Devadurga talukas in Raichur district.
Future potential
Nearly 2000 MW capacity pumped hydroelectric energy storage (PHES) plant can be installed using the Basava Sagara reservoir as its upper reservoir. In the downstream of the dam, lower reservoir with 5 tmcft storage capacity can be located to utilize nearly 60 meters water head. PHES plant is a low cost method to store the excess power generated by the solar and wind power plants during the day time and make available for use during the night hours. Also substantial secondary hydro power can be generated using the flood water flows at no extra cost during the monsoon season. Also the downstream dam with 5 tmcft storage can have 200 MW hydro power capacity to generate secondary power from floodwaters during the monsoon season.
Incidents
In 1992, two of the irrigation gates partially failed. In 2005, there was a collapse of one of the gates in the dam and up to a lakh cusecs of water was being released before emergency actions were effective. The gate broke open on the morning of 6 October and most of the water flow was stopped by the afternoon of the 9th. Basava Sagar reservoir dropped several metres as a result.
In April 2011, farmers fearing loss of their crops staged a protest at Narayanpur dam, and forced the staff to release water after officials had shut down releases due to low rainfall and inflows. This type of protests in earlier years, such as the one in April 2005 where large numbers of police prevented the farmer's from releasing the water. As of August 2013, the project has an estimated capacity of 31.47 TMC.
See also
References
- ^ "Narayanpur Dam". Krishna Bhagya Jal Nigam Ltd. Retrieved 21 June 2016.
- ^ "Narayanpur Dam: Salient Features of Completed Project". Krishna Bhagya Jala Nigam Limited. Archived from the original on 8 February 2013.
- ^ Special correspondent (8 October 2005). "Breach raises questions about safety, maintenance of dam". The Hindu. Archived from the original on 18 February 2006.
{{cite news}}
:|author=
has generic name (help) - ^ Bhat, Suresh (3 November 2006). "A lot remains to be done for UKP". The Hindu. Archived from the original on 8 February 2013.
- ^ "radial-gate-as-a-part-of-dams-what-are-the-advantages-and-disadvantages-of-it". www.bayt.com. 3 April 2018. Retrieved 30 May 2018.
- ^ "wrpinfo". india-wris.nrsc.gov.in. 3 April 2018. Archived from the original on 23 March 2018. Retrieved 30 May 2018.
- ^ Staff (7 October 2005). "Fifth gate of Narayanpur Dam cracks open, water spews out". The Hindu. Archived from the original on 7 March 2006.
- ^ "newsite". pib.nic.in. 3 April 2018. Retrieved 30 May 2018.
- ^ Staff (10 October 2005). "Outflow from Narayanpur Dam arrested". The Hindu. Archived from the original on 20 February 2006.
- ^ Staff (19 April 2011). "Farmers forcibly release water from Narayanpur dam". The Hindu. Archived from the original on 16 June 2011.
- ^ Special correspondent (14 April 2005). "Tension in Narayanpur". The Hindu. Archived from the original on 20 April 2005.
{{cite news}}
:|author=
has generic name (help)
External links
- Photos: "Narayanpur Dam". Mysore Construction Company. Archived from the original on 9 June 2012.